35 Ill. Adm. Code 734.615
Authorization for Payment; Priority List
Section 734.615 Authorization for Payment; Priority List
a) Within
60 days after notification to an owner or operator that the application for
payment or a portion thereof has been approved by the Agency or by operation of
law, the Agency must forward to the Office of the State Comptroller in
accordance with subsection (d) or (e) of this Section a voucher in the amount
approved. If the owner or operator has filed an appeal with the Board of the
Agency's final decision on an application for payment, the Agency must have 60
days after the final resolution of the appeal to forward to the Office of the
State Comptroller a voucher in the amount ordered as a result of the appeal.
Notwithstanding the time limits imposed by this Section, the Agency must not
forward vouchers to the Office of the State Comptroller until sufficient funds
are available to issue payment.
b) The following rules must
apply regarding deductibles:
1) Any
deductible, as determined by the OSFM or the Agency, must be subtracted from
any amount approved for payment by the Agency or by operation of law, or
ordered by the Board or courts;
2) Only one deductible
must apply per occurrence;
3) If
multiple incident numbers are issued for a single site in the same calendar
year, only one deductible must apply for those incidents, even if the incidents
relate to more than one occurrence; and
4) Where
more than one deductible determination is made, the higher deductible must
apply.
c) The
Agency must instruct the Office of the State Comptroller to issue payment to
the owner or operator at the address designated in accordance with Section
734.605(b)(8) or (c) of this Part. In no case must the Agency authorize the
Office of the State Comptroller to issue payment to an agent, designee, or entity
that has conducted corrective action activities for the owner or operator.
d) For
owners or operators who have deferred site classification or corrective action
in accordance with Section 734.450 of this Part, payment must be authorized
from funds encumbered pursuant to Section 734.450(a)(6) of this Part upon
approval of the application for payment by the Agency or by operation of law.
e) For
owners or operators not electing to defer site investigation or corrective
action in accordance with Section 734.450 of this Part, the Agency must form a
priority list for payment for the issuance of vouchers pursuant to subsection
(a) of this Section.
1) All
such applications for payment must be assigned a date that is the date upon
which the complete application for partial or final payment was received by the
Agency. This date must determine the owner's or operator's priority for
payment in accordance with subsection (e)(2) of this Section, with the earliest
dates receiving the highest priority.
2) Once payment
is approved by the Agency or by operation of law or ordered by the Board or
courts, the application for payment must be assigned priority in accordance
with subsection (e)(1) of this Section. The assigned date must be the only
factor determining the priority for payment for those applications approved for
payment.