35 Ill. Adm. Code 734.660
Determination and Collection of Excess Payments
Section 734.660 Determination and Collection of Excess
Payments
a) If,
for any reason, the Agency determines that an excess payment has been paid from
the Fund, the Agency may take steps to collect the excess amount pursuant to
subsection (c) of this Section.
1) Upon
identifying an excess payment, the Agency must notify the owner or operator
receiving the excess payment by certified or registered mail, return receipt
requested.
2) The
notification letter must state the amount of the excess payment and the basis
for the Agency's determination that the payment is in error.
3) The
Agency's determination of an excess payment must be subject to appeal to the
Board in the manner provided for the review of permit decisions in Section 40
of the Act.
b) An excess payment from
the Fund includes, but is not limited to:
1) Payment for a
non-corrective action cost;
2) Payment
in excess of the limitations on payments set forth in Sections 734.620 and
734.635 and Subpart H of this Part;
3) Payment received through
fraudulent means;
4) Payment calculated on
the basis of an arithmetic error;
5) Payment calculated by
the Agency in reliance on incorrect information; or
6) Payment of costs that
are not eligible for payment.
c) Excess payments may be collected
using any of the following procedures:
1) Upon
notification of the determination of an excess payment in accordance with
subsection (a) of this Section or pursuant to a Board order affirming such
determination upon appeal, the Agency may attempt to negotiate a payment
schedule with the owner or operator. Nothing in this subsection (c)(1) of this
Section must prohibit the Agency from exercising at any time its options at
subsection (c)(2) or (c)(3) of this Section or any other collection methods available
to the Agency by law.
2) If an
owner or operator submits a subsequent claim for payment after previously
receiving an excess payment from the Fund, the Agency may deduct the excess
payment amount from any subsequently approved payment amount. If the amount
subsequently approved is insufficient to recover the entire amount of the
excess payment, the Agency may use the procedures in this Section or any other
collection methods available to the Agency by law to collect the remainder.
3) The
Agency may deem an excess payment amount to be a claim or debt owed the Agency,
and the Agency may use the Comptroller's Setoff System for collection of the
claim or debt in accordance with Section 10.5 of the "State Comptroller
Act." [15 ILCS 405/10.05]