35 Ill. Adm. Code 740.715
Agency Review of Application for Final Review of Remediation Costs
Section 740
Section 740.715 Agency
Review of Application for Final Review of Remediation Costs
a) The Agency shall review the application for final review of
remediation costs to determine, in accordance with Sections 740.725 and 740.730
of this Part, whether the costs incurred are remediation costs.
b) The Agency shall have 60 days after the receipt of an
application for final review to make a final determination on the application.
The Agency's record of the date of receipt of the application shall be deemed
conclusive unless a contrary date is proven by a dated, signed receipt from
registered or certified mail. The RA may waive the time for review. Submittal
of an amended application restarts the time for review.
c) Further Review by the Agency
1) If a preliminary review of a budget plan has been obtained
under Section 740.705 of this Subpart, the RA may submit, along with the
application, supporting documentation, and the applicable fee under Section
740.720 of this Subpart, a copy of the Agency's final determination on the
budget plan accompanied by a certification, signed by the RA or authorized
agent and notarized, as follows:
I,
[name of RA, if individual, or
name of authorized agent of RA], hereby certify that the actual remediation
costs incurred at the site for line items
[list line
items to which certification applies] and identified in the application for
final review of remediation costs are equal to or less than the costs approved
for the corresponding line items in the attached budget plan determination.
2) If the budget plan determination and certification are
submitted pursuant to subsection (c)(1) of this Section, the Agency may, but is
not required to, conduct further review of the certified line item costs
incurred for development and implementation of the Remedial Action Plan and may
approve such costs as submitted. The Agency's further review shall be limited
to confirming that costs approved in the Agency's budget plan determination
were actually incurred by the RA for development and implementation of the
Remedial Action Plan.
3) If the certification in subsection (c)(1) of this Section does
not apply to all line items as approved in the budget plan, the Agency shall
conduct its review of the costs for the uncertified line items as if no budget
plan had been approved. In that review, the Agency shall not reconsider the
appropriateness of any activities, materials, labor, equipment, structures or
services already approved by the Agency for the development and implementation
of the Remedial Action Plan.
d) Upon completion of the final review, the Agency shall notify
the RA in writing of its final determination to approve, disapprove or modify
the remediation costs submitted in the application. If an application is
disapproved or approved with modification of remediation costs, the written
notification shall contain the following information as applicable:
1) An explanation of the specific type of information or
documentation, if any, that the Agency deems the RA did not provide;
2) The reasons for the disapproval or modification of remediation
costs;
3) Citations to statutory or regulatory provisions upon which the
determination is based.
e) The Agency's notification of final determination shall be by
certified or registered mail postmarked with a date stamp and with return
receipt requested. The Agency's determination shall be deemed to have taken
place on the postmarked date that the notice is mailed.
f) If the Agency disapproves or modifies the application for
final review or fails to issue a final determination within the applicable
review period, the RA may, within 35 days after receipt of the final
determination or expiration of the deadline, file an appeal with the Board.
Appeals to the Board shall be in the manner provided for the review of permit
decisions in Section 40 of the Act.