35 Ill. Adm. Code 740.905
Preliminary Review of Estimated Remediation Costs
Section 740.905 Preliminary Review of Estimated
Remediation Costs
a)
A
Remediation Applicant may obtain a preliminary review of estimated remediation
costs for the development and implementation of a Remedial Action Plan
, required
under Section 740.450 of this Part,
by submitting a budget plan along with
the Remedial Action Plan
. [415 ILCS 5/58.15(B)(i)(1)]Â The Agency shall not
accept a budget plan unless a Remedial Action Plan satisfying the requirements
of Section 740.450 of this Part also has been submitted.
b)Â Â Â Â Â Â Â Â The
budget plan must be set forth on forms prescribed and provided by the Agency
and must include, but is not limited to, the following information:
1)Â Â Â Â Â Â Â Â Identification of
applicant and remediation site, including:
A)Â Â Â Â Â Â Â The
full legal name, address and telephone number of the RA, any authorized agents
acting on behalf of the RA, and any contact persons to whom inquiries and
correspondence must be addressed;
B)Â Â Â Â Â Â Â The
address, site name, tax parcel identification number(s) and Illinois inventory
identification number for the remediation site and the date of acceptance of
the site into the Site Remediation Program; and
C)Â Â Â Â Â Â Â The
Federal Employer Identification Number (FEIN) or Social Security Number (SSN)
of the RA.
2)Â Â Â Â Â Â Â Â Line
item estimates of the costs that the RA anticipates will be incurred for the
development and implementation of the Remedial Action Plan, including but not
limited to:
A)Â Â Â Â Â Â Â Site investigation
activities:
i)Â Â Â Â Â Â Â Â Â Drilling costs;
ii)Â Â Â Â Â Â Â Â Physical soil
analysis;
iii)Â Â Â Â Â Â Â Monitoring well
installation; and
iv)Â Â Â Â Â Â Â Disposal costs.
B)Â Â Â Â Â Â Â Sampling and analysis
activities:
i)Â Â Â Â Â Â Â Â Â Soil analysis costs;
ii)Â Â Â Â Â Â Â Â Groundwater analysis
costs;
iii)Â Â Â Â Â Â Â Well purging costs;
and
iv)Â Â Â Â Â Â Â Water disposal costs.
C)Â Â Â Â Â Â Â Remedial activities:
i)Â Â Â Â Â Â Â Â Â Groundwater
remediation costs;
ii)Â Â Â Â Â Â Â Â Excavation
and disposal costs;
iii)Â Â Â Â Â Â Â Land farming costs;
iv)Â Â Â Â Â Â Â Above-ground
bio-remediation costs;
v)Â Â Â Â Â Â Â Â Land application
costs;
vi)Â Â Â Â Â Â Â Low temperature
thermal treatment costs;
vii)Â Â Â Â Â Â Backfill costs; and
viii)Â Â Â Â Â In-situ soil
remediation costs.
D)Â Â Â Â Â Â Â Report preparation
costs.
3)Â Â Â Â Â Â Â Â A
certification, signed by the RA or authorized agent and notarized, as follows:
I, [name of RA, if individual, or
authorized agent of RA], hereby certify that neither ["I" if RA is
certifying or name of RA if authorized agent is certifying], nor any related
party (as described in Section 201(l) of the Illinois Income Tax Act [35 ILCS
5/201(l)]), nor any person whose tax attributes ["I" if RA is
certifying or name of RA if authorized agent is certifying] have [has]
succeeded to under Section 381 of the Internal Revenue Code, caused or
contributed in any material respect to the release or substantial threat of a
release of regulated substance(s) or pesticide(s) that are identified and
addressed in the Remedial Action Plan submitted for the site identified above.
4)Â Â Â Â Â Â Â Â The
original signature of the RA or authorized agent acting on behalf of the RA.
c)Â Â Â Â Â Â Â Â The
RA must submit the applicable fee, as provided in Section 740.920 of this
Subpart, with the budget plan, except as provided in subsections (f) and (i)(4)
of this Section.
d)Â Â Â Â Â Â Â Â Budget
plans must be mailed or delivered to the address designated by the Agency on
the forms. Requests that are hand-delivered must be delivered during the
Agency’s normal business hours.
e)
Submittal
of a budget plan must be deemed an automatic 60-day waiver of the Remedial
Action Plan deadlines set forth in
the Act and Section 740.505 of this
Part. [415 ILCS 5/58.15(B)(i)(4)]
f)
If
the Remedial Action Plan is amended by the Remediation Applicant or as a result
of Agency action, the corresponding budget plan must be revised accordingly and
resubmitted
. [415 ILCS 5/58.15(B)(i)(2)] No additional fee shall be
required for this review.
g)Â Â Â Â Â Â Â Â The following rules
apply to the Agency's review period for budget plans:
1)Â Â Â Â Â Â Â Â The
Agency's review period begins on the date of receipt of the budget plan by the
Agency. The Agency's record of the date of receipt of a budget plan shall be
deemed conclusive unless a contrary date is proven by a dated, signed receipt
from certified or registered mail.
2)Â Â Â Â Â Â Â Â In
reviewing budget plans and the Remedial Action Plans they accompany, the Agency
is subject to the deadlines set forth in Section 740.505 of this Part with an
additional 60 days, due to the automatic waiver, in accordance with subsection
(e) of this Section.
3)Â Â Â Â Â Â Â Â Submittal of an amended
plan restarts the time for review.
4)Â Â Â Â Â Â Â Â The
RA may waive the time line for review upon a request from the Agency or at the
RA's discretion.
h)
The
Agency must review the budget plan along with the Remedial Action Plan to
determine whether the estimated costs submitted are remediation costs and whether
the costs estimated for the activities are reasonable
. [415 ILCS
5/58.15(B)(i)(1)]
i)Â Â Â Â Â Â Â Â Â Upon
completion of the review,
the Agency must issue a letter to the Remediation
Applicant approving, disapproving or modifying the estimated remediation costs
submitted in the budget plan.
[415 ILCS 5/58.15(B)(i)(5)]Â The following
rules apply regarding Agency determinations:
1)Â Â Â Â Â Â Â Â The
Agency's notification of final determination shall be by certified or
registered mail postmarked with a date stamp and with return receipt
requested. The Agency's determination shall be deemed to have been made on the
postmarked date that the notice is mailed.
2)Â Â Â Â Â Â Â Â The
Agency may combine the notification of its final determination on a budget plan
with the notification of its final determination on the corresponding Remedial
Action Plan.
3)Â Â Â Â Â Â Â Â If a
budget plan is disapproved or approved with modification of estimated
remediation costs, the written notification shall contain the following
information as applicable:
A)Â Â Â Â Â Â Â An explanation
of the specific type of information or documentation, if any, that the Agency
finds the RA did not provide;
B)Â Â Â Â Â Â Â The
reasons for the disapproval or modification of estimated remediation costs; and
C)Â Â Â Â Â Â Â Citations
to statutory or regulatory provisions upon which the determination is based.
4)Â Â Â Â Â Â Â Â If
the Agency disapproves a Remedial Action Plan or approves a Remedial Action
Plan with conditions, in accordance with Subpart E of this Part, the Agency may
return the corresponding budget plan to the RA without review. If the Remedial
Action Plan is amended in response to Agency action, the RA may submit a
revised budget plan for review. No additional fee shall be required for this
review.
5)
Within
35 days after receipt of an Agency letter disapproving or modifying a budget
plan
or expiration of the Agency deadline,
the Remediation
Applicant may appeal the Agency's decision
or the Agency's failure to issue
a final determination
to the Board in the manner provided for the review of
permits in Section 40 of
the
Act
. [415 ILCS 5/58.15(B)(i)(6)]