35 Ill. Adm. Code 811.704
Closure and Post-Closure Care and Corrective Action Cost Estimates
Section 811
Section 811.704 Closure and Post-Closure
Care and Corrective Action Cost Estimates
a) Written cost estimate. The owner or operator must have a
written estimate of the cost of closure of all parts of the facility where
wastes have been deposited in accordance with the requirements of this Part;
the written closure plan, required by Section 811.110 and 35 Ill. Adm. Code
812.114; and the cost of post-closure care and plans, required by this Part and
the written post-closure care plans required by 35 Ill. Adm. Code 812.115. The
cost estimate is the total cost for closure and post-closure care.
b) The owner or operator must revise the cost estimate whenever a
change in the closure plan or post-closure care plan increases the cost
estimate.
c) The cost estimate must be based on the steps necessary for the
premature final closure of the facility on the assumed closure date.
d) The cost estimate must be based on the assumption that the
Agency will contract with a third party to implement the closure plan.
e) The cost estimate may not be reduced by allowance for the
salvage value of equipment or waste, for the resale value of land, or for the
sale of landfill gas.
f) The cost estimate must, at a minimum, include all costs for
all activities necessary to close the facility in accordance with all
requirements of this Part.
g) The Board removed this subsection (g) and revised Section
811.718 to disallow discounting for all financial assurance mechanisms but
trust funds. This statement maintains structural consistency for
cross-references in this Part to subsections (h), (j), and (k).
h) The post-closure care cost estimate must, at a minimum, be
based on the following elements in the post-closure care plan:
1) Groundwater monitoring, based on the number of monitoring
points and parameters and the frequency of sampling specified in the permit.
2) The annual cost of cover placement and stabilization,
including an estimate of the annual residual settlement and erosion control and
the cost of mowing.
3) Alternative Landfill Gas Disposal. If landfill gas is
transported to an off-site processing system, then the owner or operator must
include in the cost estimate the costs necessary to operate an onsite gas
disposal system, should access to the off-site facility become unavailable.
The cost estimate must include the following information: installation,
operation, maintenance and monitoring of an on-site gas disposal system.
4) Cost Estimates Beyond the Design Period. When a facility must
extend the post-closure care period beyond the applicable design period, the
cost estimate must be based upon such additional time and the care activities
occurring during that time.
i) This Section does not authorize the Agency to require the
owner or operator to perform any of the indicated activities upon which cost
estimates are to be based; however, if the site permit requires a closure
activity, the owner or operator must include the cost of that activity in the
cost estimate.
j) Once the owner or operator has completed an activity, the
owner or operator may file an application for significant permit modification
pursuant to 35 Ill. Adm. Code 813.201 indicating that the activity has been
completed, and zeroing that element of the cost estimate.
k) Cost Estimate for Corrective Action at MSWLF Units
1) An owner or operator of a MSWLF unit required to undertake a
corrective action program pursuant to Section 811.326 must have a detailed
written estimate, in current dollars, of the cost of hiring a third party to
perform the corrective action in accordance with the Section 811.326. The
corrective action cost estimate must account for the total costs of corrective
action activities as described in the corrective action plan for the entire
corrective action period. The owner or operator must notify the Agency that
the estimate has been placed in the operating record.
2) The owner or operator must annually adjust the estimate for
inflation until the corrective action program is completed in accordance with
Section 811.326(f).
3) The owner or operator must increase the corrective action cost
estimate and the amount of financial assurance provided pursuant to subsections
(k)(5) and (k)(6) if changes in the corrective action program or MSWLF unit
conditions increase the maximum costs of corrective action.
4) The owner or operator may reduce the amount of the corrective
action cost estimate and the amount of financial assurance provided pursuant to
subsections (k)(5) and (k)(6) if the cost estimate exceeds the maximum
remaining costs of corrective action. The owner or operator must notify the
Agency that the justification for the reduction of the corrective action cost
estimate and the amount of financial assurance has been placed in the operating
record.
5) The owner or operator of each MSWLF unit required to undertake
a corrective action program under Section 811.326 must establish, in accordance
with Section 811.706, financial assurance for the most recent corrective action
program.
6) The owner or operator must provide continuous coverage for
corrective action until released from the financial assurance requirements for
corrective action by demonstrating compliance with Section 811.326 (f) and (g).
BOARD NOTE:
Subsection (k) is derived from 40 CFR 258.73 (2017).