35 Ill. Adm. Code 750.462
Phase VI - Remedial Action - Initial Remedial Action
Section 750
Section 750.462 Phase VI
− Remedial Action − Initial Remedial Action
In some instances, initial
remedial measures can and should begin before final selection of an appropriate
remedial action if such measures are determined to be feasible and necessary to
limit exposure or threat of exposure to a significant health or environmental
hazard and if such measures are cost-effective. Compliance with Section
750.450(b) is a prerequisite to taking initial remedial measures. The
following factors should be used in determining whether initial remedial
measures are appropriate:
a) Actual or potential direct contact with hazardous substances
by nearby population. (Measures might include fences and other security
precautions.)
b) Absence of an effective drainage control system (with an
emphasis on run-on control). (Measures might include drainage ditches.)
c) Contaminated drinking water at the tap. (Measures might
include the temporary provision of an alternative water supply.)
d) Hazardous substances in drums, barrels, tanks, or other bulk
storage containers above surface posing a serious threat to public health or
the environment. (Measures might include transport of drums off-site.)
e) Highly contaminated soils largely at or near surface, posing a
serious threat to public health or the environment. (Measures might include
temporary capping or removal of highly contaminated soils from drainage areas.)
f) Serious threat of fire or explosion or other serious threat to
public health or the environment. (Measures might include stabilization of
berms, dikes or impoundments.)
g) Weather conditions that may cause substances to migrate and to
pose a serious threat to public health or the environment. (Measures might
include stabilization of berms, dikes or impoundments.)