35 Ill. Adm. Code 807.202
Operating Permits
Section 807
Section 807.202 Operating
Permits
a) New Solid Waste Management Sites.
Subject to such exemption as expressly provided in Section
21(e) of the Act (Ill. Rev. Stat. 1982, ch. 111½, par. 1021(e)) as to the
requirement of obtaining a permit, no person shall cause or allow the use or
operation of any solid waste management site for which a Development Permit is
required under Section 807.201 without an Operating Permit issued by the Agency,
except for such testing operations as may be authorized by the Development
Permit.
b) Existing Solid Waste Management Sites.
1) Subject to such exemption as expressly provided in Section
21(e) of the Act (Ill. Rev. Stat. 1981, ch. 111½, par. 1021(e)) as to the
requirement of obtaining a permit, no person shall cause or allow the use or
operation of any existing solid waste management site without an Operating
Permit issued by the Agency not later than one year after the effective date of
these Regulations.
2) All applications for Operating Permits shall be submitted to
the Agency at least 90 days prior to the date on which such permit is required;
however, the Agency may waive such provision when appropriate.
3) The Agency may, if necessary to prevent an unmanageable
workload, extend the date by which Operating Permits are required for a period
not to exceed 180 days. The Agency shall notify the persons affected and the
Board, in writing, of such extension at least ninety days in advance of the
date set forth in Section 202(b)(1).
c) Duration of Operating Permits.
All operating permits shall remain valid until the site is
completed or closed, or until revoked, as provided herein.