35 Ill. Adm. Code 807.622
Cost Estimate for Post-closure Care
Section 807
Section 807.622 Cost
Estimate for Post-closure Care
a) The operator of a disposal site must have a written estimate
of the annual current cost of post-closure monitoring and maintenance of the
site in accordance with the applicable post-closure care regulations of this
Part. The post-closure care cost estimate is calculated by multiplying the
annual cost estimate by the number of years of post-closure care required by
this Part. The post-closure care cost estimate shall be a condition of the
permit.
b) Until the Agency has issued a certificate of closure for the
site, the operator must revise the post-closure care cost estimate whenever a
change in the post-closure care plan increases the cost estimate.
c) Assumptions:
1) The post-closure cost estimate must be based on the assumption
that the Agency will contract with a third party to implement the post-closure
care plan;
2) The post-closure cost estimate may not be reduced by allowance
for salvage value of equipment or waste, or for resale value of land.
d) The post-closure care cost estimate must, at a minimum,
include the following elements if required in the site permit for post-closure
care of the site:
1) Number of years of post-closure care required.
2) Groundwater monitoring:
A) Number of monitoring points;
B) Parameters to be monitored;
C) Frequency of sampling;
D) Cost per parameter per sampling.
3) Cover stabilization:
A) Estimate of the area which is expected annually to require
residual settlement or erosion control work;
B) Annual cost of residual settlement and erosion control work;
C) Annual cost of mowing.
e) This Section does not grant authority to the Agency to require
the operator to perform any of the indicated activities; however, if the site
permit requires a closure activity, the operator must include the cost in the
cost estimate. Once the operator has completed an activity, the operator may
file a permit application indicating that the activity has been completed, and
zeroing that element of the cost estimate.