35 Ill. Adm. Code 811.306
Liner Systems
Section 811
Section 811.306 Liner
Systems
a) All units shall be equipped with a leachate drainage and
collection system and a compacted earth liner designed as an integrated system
in compliance with the requirements of this Section and of Sections 811.307 and
811.308.
b) The liner and leachate collection system shall be stable
during all phases of construction and operation. The side slopes shall achieve
a minimum static safety factor of 1.3 and a minimum seismic safety factor of
1.0 at all times.
c) The liner shall be designed to function for the entire design
period.
d) Compacted Earth Liner Standards
1) The minimum allowable thickness shall be 1.52 meters (5 feet).
2) The liner shall be compacted to achieve a maximum hydraulic
conductivity of 1 X 10
-7
centimeters per second.
3) The construction and compaction of the liner shall be carried
out in accordance with the construction quality assurance procedures of Subpart
E so as to reduce void spaces and allow the liner to support the loadings
imposed by the waste disposal operation without settling that causes or
contributes to the failure of the leachate collection system.
4) The liner shall be constructed from materials whose properties
are not affected by contact with the constituents of the leachate expected to
be produced.
5) Alternative specifications, using standard construction
techniques, for hydraulic conductivity and liner thickness may be utilized
under the following conditions:
A) The liner thickness shall be no less than 1.52 meter (5 feet)
unless a composite liner consisting of a geomembrane immediately overlying a
compacted earth liner is installed. The following minimum standards shall
apply for a composite liner:
i) the geomembrane shall be no less than 60 mils in thickness
and meet the requirements of subsection (e); and
ii) the compacted earth liner shall be no less than 0.91 meter in
thickness (3 feet) and meet the requirements of subsection (d)(2) through
(d)(4).
B) The modified liner shall operate in conjunction with a leachate
drainage and collection system to achieve equivalent or superior performance to
the requirements of this subsection. Equivalent performance shall be evaluated
at maximum annual leachate flow conditions.
e) Geomembrane Liners
1) Geomembranes may be used only in conjunction with a compacted
earth liner system meeting the requirements of subsection (d) and a leachate
drainage and collection system meeting the requirements of Sections 811.307 and
811.308.
2) The geomembrane shall be supported by a compacted base free
from sharp objects. The geomembrane shall be chemically compatible with the
supporting soil materials.
3) The geomembrane material shall be compatible with the leachate
expected to be generated.
4) Geomembranes shall have sufficient strength and durability to
function at the site for the design period under the maximum expected loadings
imposed by the waste and equipment and stresses imposed by settlement,
temperature, construction and operation.
5) Seams shall be made in the field according to the
manufacturer's specifications. All sections shall be arranged so that the use
of field seams is minimized and seams are oriented in the direction subject to
the least amount of stress.
6) The leachate collection system shall be designed to avoid loss
of leachate through openings in the geomembrane.
f) Slurry Trenches and Cutoff Walls Used to Prevent Migration of
Leachate
1) Slurry trenches and cutoff walls built to contain leachate
migration shall be used only in conjunction with a compacted earth liner and a
leachate drainage system meeting the requirements of subsection (d) and Section
811.307 or as part of a remedial action required by Section 811.319.
2) Slurry trenches and cutoff walls shall extend into the bottom
confining layer to a depth that will establish and maintain a continuous
hydraulic connection and prevent seepage.
3) Exploration borings shall be drilled along the route of the
slurry trench or cutoff wall to confirm the depth to the confining layer. In
situ tests shall be conducted to determine the hydraulic conductivity of the
confining layer.
4) Slurry trenches and cutoff walls shall be stable under all
conditions during the design period of the facility. They shall not be
susceptible to displacement or erosion under stress or hydraulic gradient.
5) Slurry trenches and cutoff walls shall be constructed in
conformance to a construction quality assurance plan, pursuant to Subpart E,
that insures that all material and construction methods meet design
specifications.
g) The owner or operator may utilize liner configurations other
than those specified in this Section, special construction techniques and
admixtures provided that:
1) The alternative technology or material provides equivalent, or
superior, performance to the requirements of this Section;
2) The technology or material has been successfully utilized in
at least one application similar to the proposed application; and
3) Methods for manufacturing quality control and construction
quality assurance can be implemented.