35 Ill. Adm. Code 820.306
Certification of Closure and Termination of Permit
Section 820.306 Certification of Closure and Termination
of Permit
a) Within
45 calendar days after completing closure activities, the owner or operator of
a GCDD recovery facility must submit to the Agency:
1) Documentation
concerning the closure of the GCDD recovery facility that demonstrates
compliance with the Act and this Part and the date closure was completed.
2) An
affidavit by the owner or operator certifying that the GCDD recovery
facility
has been closed in compliance with the Act and this Part.
b) Under
Section 39(a) of the Act, when the Agency determines, based on information
received under subsection (a) and any Agency site inspection, that the GCDD
recovery facility has been closed in compliance with the requirements of the
Act and this Part, the Agency must notify the owner or operator in writing
that:
1) The
GCDD recovery facility permit is terminated; and
2) The
GCDD recovery facility is no longer required to maintain financial assurance
for closure of the site.
c) The
owner or operator may consider the Agency action under this Section as a denial
or grant of a permit with conditions for purposes of appeal under Section 40 of
the Act.