35 Ill. Adm. Code 845.940
Revision of Cost Estimates
Section 845.940 Revision of Cost Estimates
a) During
the active life of the CCR surface impoundment, the owner or operator must
adjust the cost estimates for closure, post-closure care, and corrective action
for inflation on an annual basis. The adjustments must occur
within 60
days before the anniversary date of the establishment of the financial
instruments used to comply with Section 845.950. The adjustment may be made by
recalculating the maximum costs of closure, post-closure care, or corrective
action in current dollars, or by using an inflation factor derived from the
annual Implicit Price Deflator for Gross National Product (Deflator) as
published by the U.S. Department of Commerce in its Survey of Current Business
(Table 1.1.9) (see subsections (a)(1) and (a)(2)). The inflation factor is the
result of dividing the latest published annual Deflator by the Deflator for the
previous year.
1) The first
adjustment is made by multiplying the cost estimate by the inflation factor.
The result is the adjusted cost estimate.
2) Subsequent
adjustments are made by multiplying the latest adjusted cost estimate by the
latest inflation factor.
b)
During
the active life of the CCR surface impoundment, the owner or operator must
revise the cost estimate within 30 days after the Agency has approved a request
to modify the
corrective action
plan,
closure plan, or post-closure care plan, if the change in the
modified plan increases the cost of corrective action, closure or post-closure
care. The revised cost estimate must be adjusted for inflation (see subsection
(a)).
c) At least 60 days
before submitting any closure plan to the Agency, the owner or operator must
revise the cost estimate if the selected closure method increases the estimated
closure or post-closure care costs.
d) The owner or
operator must keep the most current cost estimates in the facility's operating
record during the operating life of the CCR surface impoundment.