35 Ill. Adm. Code 887.245
Grantee Responsibilities
Section 887
Section 887.245 Grantee
Responsibilities
a) Prior to contracting with a Community Visioning Facilitator,
the grantee must submit to the Agency documentation demonstrating that the
facilitator has the minimum qualifications for a Community Visioning
Facilitator as set forth in Section 887.105 of this Part.
b) Within 45 days after contracting with a Community Visioning
Facilitator, the grantee must submit to the Agency a timeline for the visioning
process. The timeline must show each task that will be performed in completing
the visioning process and the key personnel associated with each task.
c) The grantee must develop an environmental vision and
strategies for achieving the environmental vision through a community
environmental visioning process that is led by a Community Visioning
Facilitator.
d) As part of the visioning process the grantee must form a
stakeholder group that, to the greatest extent practicable, includes
representatives from all segments of the community, represents the community's
diversity in terms of age, race, gender, location of residence and location of
employment, and includes persons, groups and organizations that traditionally
have not participated in community planning.
1) Community sectors that should be considered when forming the
stakeholder group include, but are not limited to: agriculture, banking,
chambers of commerce, commercial clubs, churches, civic organizations,
community improvement or betterment groups, elderly citizens, health care,
industry, libraries, local development organizations, local government, real
estate, residents, retail business, schools, utilities and youth.
2) The stakeholder group shall form the core planning group for
the visioning process and, with input from the community, perform a community
self-evaluation, create the community's environmental vision and develop
strategies for achieving the environmental vision.
e) The grantee must, to the greatest extent practicable, keep
persons from all segments of the community involved in the visioning process
and solicit input from all persons in the community. Methods of soliciting
input may include, but are not limited to, surveys, focus groups, community
forums and flyers.
f) The grantee must, to the greatest extent practicable, keep all
segments of the community informed of the progress and status of the visioning
process. Methods of providing information about the visioning process include,
but are not limited to, a speaker's bureau, articles in a local paper,
leaflets, mailings, newsletters, public service announcements, information
booths, press releases and web sites.
g) The grantee must submit quarterly progress reports to the
Agency during the term of the grant. Each report shall contain a short
narrative of the activities performed during the quarter, the dates each
activity was performed and an accounting of all grant funds expended during the
quarter.
1) The reports shall cover the following time periods: January 1
through March 31, April 1 through June 30, July 1 through September 30, and
October 1 through December 31.
2) Reports are due within 30 days after the end of the reported
quarter.
h) At the completion of the visioning process the grantee must
submit a detailed final report to the Agency that can be made available to
other communities for guidance. The final report must include, but is not
limited to, the following:
1) A description of the methods used to encourage residents of
the community to participate in the visioning process and a discussion of their
participation;
2) A characterization of the community's environmental strengths
and challenges, along with forces and trends that may impact the community's
environment in the future;
3) The environmental vision developed by the community;
4) The strategies developed by the community to achieve its
environmental vision;
5) Identification of benchmarks that can be used to measure the
community's progress toward achieving its environmental vision;
6) A discussion of the successful and unsuccessful aspects of the
visioning process; and
7) A summary of the costs incurred in completing the visioning
process.
i) If the grantee fails to timely submit a quarterly progress
report or a final report, the Agency may impose any of the sanctions set forth
in Subpart C of this Part.