44 Ill. Adm. Code 1150.300
Award and Execution of Contract
Section 1150
Section 1150.300 Award and
Execution of Contract
a) Consideration of Proposals
1) After the proposals are opened and read, they will be compared
on the basis of the summation of the products of the quantities shown in the
bid schedule by the unit bid prices. In the event of a discrepancy between
unit bid prices and extensions, the unit bid price shall govern. In awarding
contracts, the Department will, in addition to considering the amounts stated
in the proposals, take into consideration the responsibility of the various
bidders as determined by the Department of Transportation under Section
1150.200(a), and from other investigations which the Department shall make when
it has reason to believe that any of the conditions found in Sections
1150.200(a)(4) and (j) exist.
2) The right is reserved to reject any or all proposals, to waive
technicalities, or to advertise for new proposals, if, in the judgment of the
Department, the best interests of the Department will be served.
b) Award of Contract
1) The award of contract will be made within 45 calendar days
after the opening of proposals to the lowest responsible and qualified bidder
whose proposal complies with all the requirements prescribed. The successful
bidder will be notified by letter of intent that his/her bid has been accepted,
and that, subject to subsections (b)(2) and (3) of this Section, the bidder
will be the Contractor.
2) An approved contract executed by the Department is required
before the State is bound. An award may be cancelled by the Department any
time prior to execution in order to protect the public interest and integrity
of the bidding process or for any other reason if, in the judgment of the
Department, the best interest of the Department will be served.
3) If a contract is not awarded within 45 days after the opening
of proposals, a bidder may file a written request with the Department for the
withdrawal of his/her bid, and the Department will permit such withdrawal.
Provided, however, if the Notice to Bidders specifies a period longer than 45
days after the opening of proposals, to delay the award of contract to coincide
with the AML federal grant award, then the time shall be as specified for
withdrawal of bids.
c) Notice of Contract Awarded
Notice of each
and every contract that is let or awarded shall be published in the next
available Illinois Procurement Bulletin.
d) Return of Proposal Guaranty
1) The proposal guaranty checks of all except the two lowest
bidders will be returned promptly after the proposals have been checked,
tabulated, and the relation of the proposals established. Proposal guaranty
checks of the two lowest bidders will be returned as soon as the contract and
contract bond of the successful bidder have been properly executed and
approved. Bid bonds will not be returned.
2) After a period of 3 working days after the date of opening
proposals has elapsed, the Department shall permit the two lowest bidders to
substitute for the bank cashier's checks or certified checks submitted with
their proposals as proposal guaranties, bid bonds on the Department forms
executed by corporate surety companies satisfactory to the Department.
e) Applicant Violator System
1) Under 30 CFR 874.16, every successful bidder for a federally
funded AML contract must be eligible under 30 CFR 773.15(b)(1) at the time of
contract award to receive a permit or conditional permit to conduct surface
coal mining operations. Bidder eligibility must be confirmed by the federal
Office of Surface Mining, Reclamation and Enforcement's automated
Applicant/Violator System (AVS) for each contract to be awarded.
2) At the time the successful bidder is notified by letter of
intent that his/her bid will be accepted, the Department will provide to the
bidder an Ownership/Control ("O/C") information package. The bidder
shall completely fill out the forms and return the completed forms to the
Department. The Department will forward the completed forms to OSM at the
Lexington, Kentucky AVS office for data entry and compliance check.
3) All subcontractors who will receive 10% or more of the total
contact funding will also be required to submit an O/C information package and
be subject to the OSM/AVS compliance check, prior to receiving the Department's
approval of subcontractor.
4) Any contract inspector, selected through a bidding process,
regardless of the percentage of contract funding, will also be required to
submit an O/C information package and be subject to the OSM/AVS compliance
check.
5) The Department shall deny a contract and cancel the award upon
OSM's recommendation that the successful bidder is not eligible for an AML
contract. The Department shall deny approval of subcontractor upon OSM's
recommendation that the subcontractor is not eligible for an AML contract. The
Department shall deny an inspection contract upon OSM's recommendation that the
contract inspector is not eligible for an AML contract.
6) Any person denied an AML contract, or participation in an AML
funded project, shall appeal the decision and recommendation of OSM directly to
OSM. Appeal should be made to establish eligibility for future AML projects.
The Department will not delay a project pending appeal. The Department's role
in the AVS compliance check process is ministerial and does not involve
exercise of independent judgment or review of OSM's decision and
recommendation. The Department shall not be responsible for any damages sustained
by any person by reason of OSM's determination as to eligibility for AML
contracts.
7) After a Contractor, subcontractor, or contract inspector has
once submitted an O/C information package and has been entered into the AVS in
connection with an AML project, the Department may, in connection with
subsequent projects, provide dated AVS printouts reflecting the information
submitted and the current AVS recommendation, along with an AML Contractor O/C
Data Certification form. The Contractor, subcontractor, or contract inspector
shall complete and submit the certification in place of the O/C information
package, in the same manner as provided above.
8) Any potential AML Contractor, subcontractor or contract
inspector may submit O/C information directly to OSM at the Lexington AVS
Office, to predetermine eligibility for AML contracts.
f) Requirement of Contract Bond
The Contractor
shall furnish the Department a performance and payment bond with good and
sufficient sureties in the full amount of the contract as the penal sum. The
surety shall be acceptable to the Department, shall waive notice of any changes
and extensions of time, and shall submit its bond on the form furnished by the
Department.
g) Execution of Contract
1) The contract shall be executed by the successful bidder and
returned, together with the Contract Bond, within 15 days after the contract
has been mailed to the bidder.
2) If the bidder to whom award is made is a corporation organized
under the laws of a State other than Illinois, the bidder shall furnish the
Department a copy of the corporation's Certificate of Authority to do business
in the State of Illinois with the return of the executed contract and bond.
Failure to furnish such evidence of a Certificate of Authority within the time
required will be considered as just cause for the annulment of the award and
the forfeiture of the proposal guaranty to the State, not as a penalty, but in
payment of liquidated damages sustained as a result of such failure.
h) Failure to Execute Contract
1) If the contract is not executed by the Department within 15
days following receipt from the bidder of the properly executed contracts and
bonds, the bidder shall have the right to withdraw his/her bid without penalty.
2) Failure of the successful bidder to execute the contract and
file acceptable bonds within 15 days after the contract has been mailed to the
bidder shall be just cause for the cancellation of the award and the forfeiture
of the proposal guaranty which shall become the property of the Department, not
as a penalty, but in liquidation of damages sustained. Award may then be made
to the next lowest responsible bidder, or the work may be readvertised
considering the time available for readvertisement, the number of bids received
and the variance in the amount of the bids received.
i) Termination of Contracts
1) The Department shall, by written order, terminate the contract
or any portion thereof after determining that for reasons beyond the control of
the parties, the Contractor is prevented from proceeding with or completing the
work as originally contracted for, and that termination would, therefore, be in
the public interest. Such reasons for termination may include, but need not be
necessarily limited to, Executive Orders of the President relating to
prosecution of war or national defense, national emergency which creates a
serious shortage of materials, orders from duly constituted authorities
relating to energy conservation, and restraining orders or injunctions obtained
by third-party citizen action resulting from national or local environmental
protection laws or where the issuance of such order or injunction is primarily
caused by acts or omissions of persons or agencies other than the Contractor.
2) When contracts, or any portion thereof, are definitely
terminated or cancelled, and the Contractor released before all items of work
included in his/her contract have been completed, payment will be made for the
actual number of units of items of work completed at contract unit prices, or
as specified in the contract for partially completed items, and no claims for
loss of anticipated profits shall be considered. Reimbursement for
organization of the work and moving equipment to and from the job will be made
when the volume of the work completed is too small to compensate the Contractor
for these expenses under the contract unit prices, the intent being that an
equitable settlement will be made with the Contractor.
3) Acceptable materials, obtained by the Contractor for the work,
that have been inspected, tested and accepted by the Department, and that are
not incorporated in the work shall be purchased from the Contractor at actual
costs as shown by receipted bills and actual cost records at such points of
delivery as may be designated by the Department, when the Department determines
that the materials cannot be returned or resold by the Contractor and the
Department or other State agency can make use of such material.
4) Termination of a contract, as stated above, will not relieve
the Contractor or his/her surety of the responsibility of replacing defective
work as required by the contract.