44 Ill. Adm. Code 1150.1100
Evaluation Procedure
Section 1150
Section 1150.1100 Evaluation
Procedure
a) A selection committee, consisting of the Director of the
Office of Mines and Minerals, the Manager of the AML Reclamation Division, and
the Supervisor of the Project Management Section, or their designees, shall
select firms to provide architectural, engineering, and land surveying services
on AML reclamation projects. The Committee shall evaluate the Proposals,
taking into consideration the following qualification factors:
1) Ability of professional personnel.
2) Past record and experience on AML projects and projects with
similar professional disciplinary requirements.
3) Performance data on file.
4) Willingness to meet time requirements.
5) Location of the Consultant's office in relation to the project
site and the Department's AML office that will be managing the project.
6) Workload of the Consultant.
7) Any other qualifications based factors as the Department may
determine in writing are applicable on a project specific basis.
b) The Committee shall assign AML technical staff, having knowledge
of the scope of work requirements, to provide preliminary technical review as
necessary and appropriate to assure that all project considerations are taken
into account.
c) The Committee shall not seek formal or informal submission of
verbal or written estimates of costs or proposals in terms of dollars, hours
required, percentage of construction cost, or any other measure of compensation
prior to selecting a firm for negotiation.
d) The Committee may conduct discussions with and require public presentations
by Consultants deemed to be the most qualified regarding their qualifications,
approach to the project and ability to furnish the required services.