44 Ill. Adm. Code 1150.500
Emergency Contracting
Section 1150
Section 1150.500 Emergency
Contracting
a) Waiver of Bidding Procedures
When any
abandoned mine condition involves a danger to public health and safety and
cannot await abatement under normal program procedures, the Department shall
waive the prequalification and bidding procedures of Section 1150.300 and the
Department shall enter into construction contracts for abatement of the
dangerous condition pursuant to the provisions of this Subpart.
b) Use of Prequalified Contractors
1) The Department shall maintain a list, revised at least
annually, of contractors who are prequalified with the Department of
Transportation for the type of construction work encountered in AML Emergency
reclamation projects. The list shall also include Contractors who have
demonstrated responsibility and competence through past performance on AML Emergency
reclamation projects. Listed contractors shall be used on all projects unless:
A) the particular construction activity involved is not of a type
normally performed by the listed Contractors; or
B) listed contractors cannot be contacted within a reasonable
time; or
C) listed contractors are not available to begin work within a
reasonable time.
2) What constitutes a "reasonable time" shall be
determined by the severity of the emergency or dangerous condition, and the
cost of temporary protective measures.
3) When listed contractors cannot be used, the Department may use
any responsible contractor who appears to be qualified based upon the
contractor's reputation, experience, and available equipment.
c) Obtaining Bids
1) When the full bidding procedures of Section 1150.300 will not
be utilized, the Department shall attempt to contact at least three available
contractors to request proposals. The three contractors to be contacted shall
be selected based upon proximity to the project, past experience, expertise and
available equipment and manpower.
2) When inspection of the site conditions is necessary to
understand the detail or complexity of the project, or when requested by a
contractor, a pre-bid meeting may be held for interested contractors where the
project will be explained and proposal documents distributed. The pre-bid
meeting shall be held at the project site whenever possible.
3) Interested contractors shall submit their proposals on the
provided bid documents.
d) Contents of Proposal Documents
1) When full bidding procedures will not be utilized, the
proposal documents will include:
A) The unsigned agreement, and all attachments thereto,
B) Plans, specifications, and any supplemental specifications, and
C) The itemized bid form to be filled out by the Contractor.
2) The itemized bid form shall become the Contractor's proposal
upon completion and execution by the Contractor.
e) Award and Execution of Contract
The contract
shall be awarded to the lowest responsible bidder considering conformity with
specifications, availability for work and suitability of equipment.