44 Ill. Adm. Code 1300.5060
Voidable Contracts
Section 1300.5060 Voidable Contracts
If the CPO identifies, discovers, or reasonably suspects
that a false certification or inaccurate, incomplete, or misleading disclosure
has been made by a contractor or a subcontractor for any of the certifications
or disclosures required under Article 50 of the Code, the CPO shall notify the
OAG PPCMB and provide it with a copy of the contract or other procurement
document in question. If the OAG PPCMB
finds evidence of a
false
certification or inaccurate, incomplete, or misleading disclosure, the OAG PPCMB
shall provide written notice to the bidder, offeror, potential contractor, contractor
or subcontractor that is identified, discovered, or reasonably suspected of
making
the false certification or inaccurate, incomplete, or misleading disclosure.
The
bidder, offeror, potential contractor, contractor or subcontractor shall have
15 days to respond in writing to the
OAG PPCMB
. Upon consideration, the
OAG PPCMB
shall recommend, in writing, whether to allow or void the
contract, bid, offer, or subcontract weighing the best interest of the State of
Illinois. All recommendations shall be submitted to the
Attorney General,
or his or her designee, for final review and to the Inspector General and the
CPO.