44 Ill. Adm. Code 4.1005
Procurement Authority
Section 4.1005 Procurement
Authority
a) The CPO-HE appointed by the Executive Ethics Commission will
exercise the procurement authority created by the Code for the benefit of the
State of Illinois and the universities under the jurisdiction of the CPO. The
Executive Ethics Commission may appoint a temporary acting CPO to act in the
absence of the CPO-HE, such as during illness, vacation or other extended
leave.
b) The CPO-HE's procurement authority extends to supplies,
services, construction not under the jurisdiction of the Capital Development
Board or the Department of Transportation, real estate leases and all other
categories of need subject to the Code. The authority extends to all aspects
of the procurement process, including, but not limited to: pre-solicitation
activities, solicitation preparation, source selection, evaluation, award,
approval or rejection of proposed contracts, dispute resolution and records
subsequent to identification of need, except as otherwise provided for in the
Code.
c) Any reference in the Code or this Part directing or
authorizing a university to take procurement action is subject to the overall
procurement authority of the CPO-HE and SPO as set forth in the Code and this
Part.
d) The CPO-HE exercises procurement authority through one or more
SPOs or temporary acting SPOs and university and other staff assigned to the
procurement function. The CPO-HE may assign an SPO to one or more universities
or may make assignments on a functional basis. The CPO-HE may appoint a
temporary acting SPO with limited authority to act with an appointed SPO. In
the absence of an appointed SPO, the CPO-HE may exercise the procurement
authority of an SPO or may appoint a temporary acting SPO. Unless the Code or
this Part prohibits a designee from performing a procurement action, the CPO-HE
may delegate procurement action to an SPO or other designee. The CPO-HE may
reserve certain procurement activities to the CPO-HE and reserves the right to
review and modify or overturn any action of an SPO or any other designee.
e) An SPO will exercise procurement authority in accordance with
direction and limitations established by the CPO-HE. SPOs have roles and
responsibilities established in Section 10-10 of the Code. Each university
shall recognize the SPOs' statutory roles and shall cooperate with SPOs in the
conduct of their actions. The SPO will act primarily to review, authorize and
approve university procurement actions. The CPO-HE will determine and
identify, in writing, procurement activities that must be conducted by the
CPO-HE or an SPO. Activities not reserved to the CPO-HE or SPO will be
conducted by the university staff with CPO-HE/SPO oversight.
f) Each university shall determine an appropriate number of qualified
staff and related resources to meet the procurement needs of the university.
University staff remain university employees at all times, including while
acting under authority of the CPO-HE.
g) The university is responsible for determining the need for a
particular procurement. If the SPO or CPO-HE has a question regarding the need
for a particular procurement, the SPO or CPO-HE may require a signed statement
from a university official outside the procurement office confirming that the
proposed procurement for the stated need is in the best interest of the
university.
h) University procurement staff are responsible for:
1) ensuring that all procurement activities, including those
submitted to the SPO or CPO-HE for review, authorization or approval, are in
accordance with the Code, this Part, other applicable laws and rules, the
policy direction of the CPO-HE and internal policies of the university; and
2) obtaining all State and university approvals applicable to the
particular stage of the procurement process.
i) The CPO-HE and the SPO, at the direction of the CPO-HE, has
the authority to review any contract or contract amendment prior to execution
to ensure that applicable procurement and contracting standards were followed
and approve or reject
proposed
contracts for a purchasing agency
. [30
ILCS 500/10-10(a)]. In addition to this authority, the CPO-HE may authorize a
university to enter into contracts without specific approval of the CPO-HE or
SPO.
1) The CPO-HE shall determine in writing which contracts must be
reviewed by the CPO-HE or SPO for approval or rejection prior to execution by
the university. These approval authorities may be modified or revoked at any
time by the CPO-HE or the SPO, when appropriate. In the absence of written
direction, the university shall enter into contracts for its needs.
2) Any written determination regarding approval authorization by
the CPO‑HE or SPO shall be maintained by the CPO-HE and distributed to
the SPO, university head, university purchasing director and the State
Comptroller.
3) Because all fiscal authority for the universities is vested in
their governing boards under their organizing statutes, only those contracts
signed in accordance with board of trustees procedures are valid obligations of
a university. If the CPO-HE or SPO approves a proposed contract, the
university must sign in order for the contract to be legally binding on the
university. The university may decline to sign a contract even if approved by
the CPO-HE or SPO.
4) If the CPO-HE or SPO approves a proposed contract for a
university, in no event shall the CPO-HE or SPO have or assume any
responsibility or obligation under the contract, financial or otherwise, to any
party or person.
j) Procurement Compliance Monitors (PCMs)
1) PCMs have roles and responsibilities established in Section
10-15 of the Code. This includes overseeing and reviewing the procurement
process, having access to records and systems, and attending any procurement
meeting.
2) Each university shall recognize these statutory roles and
shall cooperate with PCMs in the conduct of their actions. Cooperation
includes providing notice of, and access to, procurement meetings and access to
all procurement related records in whatever format they may exist, including
documents, databases and systems. Failure to cooperate and resolve issues may
be reported to the chief executive officer of the university and in certain
cases may require reporting to the Office of the Executive Inspector General.
3) Should a PCM request review of a contract before final
execution, the university shall not execute the contract until approved by the
SPO after consultation with the PCM and the university.
k) Inquiries
Any offeror,
respondent, SPO, State agency, university, subcontractor or person may contact
the CPO-HE at http://www.cpohe.illinois.gov
concerning any
procurement matter and obtain information concerning the procurement process or
a pending procurement to meet the objectives of Section 1-5 of the Code and
Section 4.5 of this Part. The CPO-HE shall take all measures, within its means
and resources, in conformity with the Code and this Part, to address any
inquiries to effectuate the aims of the Code and this Part. All contacts shall
be placed in the procurement file and in compliance with Section 50-39 of the
Code.
l) Notification
In
consultation with the CPO-HE, an SPO or PCM shall advise a university in
writing of any misconduct, waste or inefficiency with respect to a university
procurement and give the university opportunity to correct or resolve the
issue. If the university does not correct the issue, the SPO or PCM shall
report the problem to the Office of the Inspector General and the CPO-HE. The
Attorney General's Office shall also be notified if collusion or other
anticompetitive practice is suspected.