44 Ill. Adm. Code 750.220
Construction Employee Utilization Projection
Section 750
Section 750.220 Construction
Employee Utilization Projection
a) All bidders on construction contracts subject to the
requirements of the Illinois Purchasing Act (Ill. Rev. Stat. ch. 127, pars.
132.1 et seq., as hereafter amended) shall complete and submit along with and
as part of their bids, a Bidder's Employee Utilization Form – Construction
(Form PC-2) setting forth a projection and breakdown of the total workforce
intended to be hired and/or allocated to such contract work by the bidder
including a projection of minority and female employee utilization in all job
classifications on the contract project. A contracting agency may, however,
with the approval of the Department, modify the Form PC-2 for use with some or
all of its contracts without impairing compliance with this Section.
b) The contracting agency letting such a contract shall review
the Employee Utilization Form, and workforce projections contained therein, of
the contract awardee to determine if such projections reflect an
underutilization of minority persons and/or women in any job classification in
accordance with the Equal Employment Opportunity Clause and Section 750.120 of
this Part. If it is determined that the contract awardee's projections reflect
an underutilization of minority persons and/or women in any job classification,
the agency shall confer and negotiate with the awardee to obtain satisfactory
projections as a prerequisite to commencement of the contract work. The
awardee may be required to develop an acceptable written affirmative action
plan to correct such underutilization including a specific timetable geared to
the completion stages of the contract.
c) The contracting agency shall provide to the Department a copy
of the contract awardee's Employee Utilization Form, including any revisions as
may be negotiated by the agency and a copy of any required written affirmative
action plan. The Department may review and revise any action taken by the
contracting agency with respect to the requirements of this Section; provided
that the Department may from time to time enter into agreements with individual
contracting agencies whose compliance programs meet with its approval whereby
utilization projections accepted by such agencies shall be accorded substantial
weight by the Department. A contractor's utilization projections approved under
this Section shall constitute goals which the contractor shall make all good
faith efforts to achieve, but such goals may be subject to later revision among
the parties to reflect fluctuations in the available minority and female labor
forces.
d) Upon the written request of a contracting agency, which
request shall state the reasons therefor, the Department may exempt any person
from the requirements of subsection (a) of this Section when it deems that
exceptional circumstances and the public interest so require. Such exemption
shall be granted for a specified purpose and duration but may be withdrawn by
the Department at any time; provided however, that such withdrawal of exemption
shall not apply to contracts awarded prior to the withdrawal.