44 Ill. Adm. Code 8.3115
Award of Design-Build Contract
Section 8.3115Â Award of Design-Build Contract
a)Â Â Â Â Â Â Â Â CDB
may award the DB contract to the highest overall ranked entity based on the
Phase 2 submissions.
b)Â Â Â Â Â Â Â Â Notice
of award shall be made in writing. Unsuccessful entities shall also be
notified in writing.
c)Â Â Â Â Â Â Â Â CDB may not request a
best and final offer after the receipt of proposals.
d)Â Â Â Â Â Â Â Â CDB
may negotiate with the selected DB entity after award, but prior to contract
execution, for the purpose of securing better terms than originally proposed,
provided that the salient features of the RFP are not diminished.