44 Ill. Adm. Code 8.5620
Violation of Statute or Rule
Section 8.5620Â Violation of Statute or Rule
a)Â Â Â Â Â Â Â Â Determination
that Solicitation or Award Violates Statute or Rule
If CDB determines or suspects that
the solicitation or proposed award is in violation of statute or rule, it shall
report the circumstances to the CPO or SPO. If the CPO or the SPO finds that
the solicitation or proposed award is in violation of statute or rule, he or
she shall report the circumstances to CDB and the CPO or SPO may cancel the
solicitation or proposed award, or make modifications to correct the violation,
if the correction may be legally accomplished.
b)Â Â Â Â Â Â Â Â Determination
that Contract Violates the Code or this Part
1)Â Â Â Â Â Â Â Â If
any contract or amendment to a contract is entered into, or purchase or
expenditure of funds is made, at any time in violation of this Part or any
other law, the contract or amendment may be declared void by the CPO or may be
ratified or affirmed, provided the CPO determines that ratification is in the
best interest of the State. If the contract is ratified and affirmed, it shall
be without prejudice to the State's right to any appropriate damages.
2)Â Â Â Â Â Â Â Â If,
during the term of a contract, the SPO determines that the contractor is
delinquent in the payment of debt as set forth in Section 50-11 of the Code,
the CPO may declare the contract void if it determines that voiding the
contract is in the best interest of the State.
3)Â Â Â Â Â Â Â Â If,
during the term of a contract, the CPO learns from an annual certification or
otherwise determines that the contractor or subcontractor no longer qualifies
to enter into State contracts, the CPO may declare the contract void if it
determines that voiding the contract is in the best interest of the State. If
the voiding is the result of an action taken by a subcontractor, the contract
shall not be void as long as the contractor terminates the subcontract.
c)Â Â Â Â Â Â Â Â Effect
of Declaring a Contract Null and Void
In all cases in which a contract
is voided, the State agency shall endeavor to return those supplies delivered
under the contract that have not been used or distributed. No further work
shall be performed under the contract. Resolution of any outstanding invoices