44 Ill. Adm. Code 8.8050
Actions Affecting Prequalification
Section 8.8050 Actions
Affecting
Prequalification
At any time, the CPO may
consider whether action should be taken concerning prequalification. Actions
that may be taken include one or more of the following:
a)Â Â Â Â Â Â Â Â Interim or Emergency Suspension or Modification
The CPO may
summarily suspend or modify a vendor's prequalification, [20 ILCS 3105/16]. A
hearing, if requested by the vendor, shall be held within 30 days.
b)Â Â Â Â Â Â Â Â Debarment
The CPO may
debar a vendor to exclude it from bidding for CDB contracts as authorized in
this Part or by statute. The period of debarment shall be not less than 5
years and may be permanent when warranted or as authorized by law. The
debarment will be effective 7 calendar days after receipt of notice unless a
request for hearing is filed. If a request for hearing is filed, suspension
shall not become effective until the CPO makes a final written determination.
c)Â Â Â Â Â Â Â Â Modification of Ability to Submit a Bid or Offer
The CPO may
modify or limit a prequalification as appropriate, including, but not limited
to, one or more of the following:
1)Â Â Â Â Â Â Â Â Limiting the dollar amount or project size for which a bid or
offer can be submitted for a specified period of time, or until a current
contract is substantially or fully complete.
2)Â Â Â Â Â Â Â Â Limiting the number of CDB contracts a vendor may enter into
for a specified period of time, or until a current contract is substantially or
fully complete.
3)Â Â Â Â Â Â Â Â Limiting the aggregate dollar amount of contracts the vendor
may enter into, considering both public and private contracts.
4)Â Â Â Â Â Â Â Â Imposing limits set forth in this subsection (c) pending
performance on the vendor's next CDB contracts, in instances in which the vendor
has no current CDB contracts.
d)Â Â Â Â Â Â Â Â Conditional Prequalification
The CPO may
condition prequalification (which may be otherwise limited) on the vendor's
successful utilization of a management plan, evaluations, conferences or other
methods designed to achieve satisfactory performance or compliance with
contract requirements.
e)Â Â Â Â Â Â Â Â Suspension
The CPO may
suspend or disqualify a vendor temporarily from contracting with CDB, for a
period of time up to 5 years. The contractor vendor's failure to timely pursue
administrative action, as provided by this Part, shall constitute consent of
the vendor to the CPO's action. The suspension will be effective 7 calendar
days after receipt of notice unless a request for hearing is filed. If a
request for hearing is filed, suspension shall not become effective until the
CPO makes a final written determination.