44 Ill. Adm. Code 950.170
Processing of Contractor Prequalification and Bidder Responsibility and Renewal Applications
Section 950
Section 950.170 Processing
of Contractor Prequalification and Bidder Responsibility and Renewal
Applications
a) New bidders and bidders nearing the prequalification
expiration date must complete a contractor prequalification and bidder
responsibility application, including the Financial Interests and Potential
Conflicts of Interest forms required under Section 50-35 of the Illinois
Procurement Code [30 ILCS 500/50-35].
b) Processing of contractor prequalification and bidder
responsibility applications by CDB may require up to 45 days when the
application information is complete and satisfactory and references are responsive.
c) Applications for renewal will be sent to contractors
approximately 60 days before the expiration of current prequalification and are
available electronically on CDB's internet site at www.cdb.state.il.us.
Contractors who do not receive an application are responsible for obtaining one
at least 45 days prior to expiration. When all information received is
complete and satisfactory, processing may take up to 45 days. When any
information is incomplete or unsatisfactory, a longer processing time will be
required. Contractors will be notified when information is incomplete or
unsatisfactory. Unless otherwise specified in writing by CDB, the term of
prequalification shall be one year. When prequalification is granted, the
contractor will be notified in writing of the expiration date, which will also
be entered on CDB's electronic program. CDB may grant a shorter term of
prequalification by agreement with the contractor, when a determination is made
that a shorter period is justified. CDB may, in its discretion, grant a longer
period of prequalification when deemed appropriate in light of recent and
relevant satisfactory project performance. Updated or new contractor
information including the term of prequalification will be entered on CDB's electronic
program weekly. The electronic program will be capable of, among other things,
sorting contractors by trade to produce lists of contractors in various
trades. At the beginning of each month, a list of contractors whose
prequalification expires in approximately 60 days will be generated.
d) Applications may be sent to CDB by facsimile.
e) CDB shall review and evaluate each application received, which
may include one or more of the following actions:
1) Reviewing to determine whether the application is filled out
in accordance with the instructions provided.
2) Contacting work references or any other possible sources of
pertinent information.
3) Requesting additional information from the applicant.
4) Reviewing CDB contractor performance evaluations.
5) Meeting with the applicant at the request of CDB or the
applicant.
f) CDB shall deny prequalification to any firm that has not
affirmatively demonstrated its responsibility. CDB's determination of
responsibility shall be final.