44 Ill. Adm. Code 950.320
Nullification of Prequalification
Section 950
Section 950.320
Nullification of
Prequalification
When CDB determines that a
contractor has knowingly made a material misrepresentation in its application
for prequalification, the contractor may not re-apply to CDB for a period of
three years.
a) When the contractor has not previously applied to CDB, or it
failed to reapply, the three year period shall begin on the date of the
submittal of the application.
b) When the contractor has been determined to be responsible in
error, the three year period shall begin on the date the current responsibility
determination was made.
c) CDB will notify the contractor of the nullity. The contractor
may, within 30 days after notification, submit a written explanation with
supporting documentation for CDB's review.
d) CDB may cancel awards or terminate any contracts awarded that
were based upon the application with misrepresentations.
e) A material misrepresentation is made by knowingly submitting
any untrue, misleading or deceptive information or document containing such
information, or by the concealment, suppression or omission of any information,
in or from an application, which causes CDB to act differently than it would
have if it had known the undisclosed or true information.