44 Ill. Adm. Code 950.370

Effect on Current Contracts

Last amended: 1998Year: 2026Length: 58 wordsOfficial source
Section 950 Section 950.370  Effect on Current Contracts Current CDB contracts may be terminated when a contractor is determined to be non-responsible and it is in the public interest to do so, whether or not the non-responsibility has a direct connection with the current contract. Contracts may be terminated with or without further action on the contractor's prequalification.