14 Ill. Adm. Code 521.50
Form of Application
Section 521.50 Form of Application
a) Applications
will be accepted at any time during the year. The Department will provide
interested applicants with an application package upon request. Submission of
an application does not commit the Department to award assistance or pay any
costs, including any application fee, incurred by the applicant in the
preparation of an application.
b) Any taxpayer
proposing a data center project either constructed or to be constructed in
Illinois may request consideration by application to the Department in which
the applicant states its intent to make a capital investment of at least
$250,000,000 and to hire at least 20 new full-time equivalent employees,
collectively between the applicant and tenants of the proposed data center,
within a specified 60-month period.
c) Written
applications are required and must be submitted on the standard application
form provided by the Department. Applications shall be submitted to the
Department office location or electronic mail address identified in the
application.
1) The application shall
include:
A) Legal
Applicant – name, address, telephone number of each applicant; key contact,
title, telephone number and electronic mail address; company Federal Employer
Identification Number (FEIN) or the Illinois Business Tax (IBT) number; and
whether the proposed project is in an underserved area. The application shall
be accompanied by a Certificate of Good Standing from the Office of the
Illinois Secretary of State for each applicant or other proof of authority to
transact business in the State.
B) Investment
Information – a detailed description of the capital investment the taxpayer or
its tenants will make in the data center project. This shall include, but is
not limited to, a summary of the eligible investment, when the qualified
property will be placed in service, and a detailed description of the applicant's
commitment to make a minimum eligible investment of at least $250,000,000, and
the applicant's plan to create at least 20 new full-time or full-time
equivalent jobs involved in the operation and maintenance of the data center,
collectively with the applicant's tenants. The applicant should include
supporting documentation regarding this investment information for the
Department to properly evaluate the project.
C) Green
Building Certification −
i) supporting
documentation that the qualified property meets the green building standards,
with the certification that designates the building as one or more of the
following: carbon neutral; BREEAM for new construction; BREEAM In-Use; ENERGY
STAR; Envision; ISO 50001-energy management; LEED for Building Design and
Construction; LEED for Operation and Maintenance; Green Globes for New
Construction; Green Globes for Existing Buildings; UL 3223; or another,
substantially equivalent, designation approved by the Department.
ii) in
the event the applicant seeks to demonstrate an alternative certification, an
explanation and supporting documentation as to how the program is "equivalent"
to those programs and categories specifically enumerated in the Act. In the
event the certification has not yet been achieved at the time of application,
the taxpayer must provide documentation pursuant to the terms of the MOU
entered into between the company and the taxpayer.
D) Job Creation
– a detailed description of the full-time and full-time equivalent jobs to be
created at the data center, including both those jobs involved in the
operations and maintenance of the data center and other positions, the annual
average wages associated with these job categories, and the actual or
anticipated start date for these positions. The application must also include
the county average annualized pay for the county in which the data center is,
or is to be, located. To the extent known at the time of application, the applicant
shall identify any tenants, actual or anticipated new hiring by the tenants,
and whether and how the new jobs will be associated with the operations or
maintenance of the data center.
E) Other
provisions – any other provisions or information that the Department determines
is necessary to facilitate the Department's evaluation of the application.
2) The
applicant shall additionally submit:
A) Tax Clearance,
as follows:
i) to
the Illinois Department of Revenue, a Form ITR-1; and
ii) to
DCEO, proof of tax clearance from the Illinois Department of Revenue.
B) Project
Labor Agreement − evidence of a project labor agreement with respect to
the project at the time of the application. If the data center has not been
constructed and when the evidentiary material is not available at the time of application,
proof of the project labor agreement must be provided to the Department
pursuant to the terms of the MOU applicable to the project.
d) The applicant
is responsible for the accuracy of all data, information and documentation required
by subsection (c). Once submitted, applications shall become the property of
the Department.
e) Any
materials or data made available or received by any agent or employee of the
Department from an applicant for, or a recipient of a tax exemption or credit
under this Part, that is exempt from disclosure under Section 7 of the Freedom
of Information Act [5 ILCS 140/7], shall not be disclosed.