14 Ill. Adm. Code 570.40
Selection for Funding
Section 570
Section 570.40 Selection for
Funding
a) Direct Funding
1) For any Direct Loan application which meets the criteria of
Section 570.30(a)(1), Department staff or designee will then conduct field
visit evaluations to verify information in the application, leading to the
final funding decision. The field visit will analyze the following:
A) an assessment of the project in terms of the employment
impact/opportunity involved, in relation to the value of the funds requested
and types of jobs preferred as described in Section 570.30(a)(1)(A)(iii);
B) an assessment of the project in terms of the modernization and
improvement of competitiveness of the company, in relation to the value of the
funds requested as described in Section 570.30(a)(1)(A)(iv);
C) a verification of submitted application information; and
D) past performance of the applicant under previous Departmental
programs, if applicable (e.g., success in previous projects and the level of
compliance with previous agreements).
2) Applications that best meet the objectives of the programs and
demonstrate the greatest potential for job creation/retention or those which
modernize or improve the competitiveness of the firm will receive loan or grant
funds, until all available funds are expended.
3) For any Technical Assistance Grant application which meets the
criteria of Section 570.30(a)(2), Department staff will verify information in
the application, leading to the final funding decision. The evaluation will
analyze the following:
A) a verification of submitted application information; and
B) past performance of the applicant under previous Departmental
programs, if applicable (e.g., success in previous projects and the level of
compliance with previous agreements).
4) A request for financial assistance to organize a Development
Corporation will be evaluated in accordance with the requirement of Section
570.30(a)(3). The review of applications will begin after the application due
date and take no more than 75 working days, with financial assistance awards
being announced at the end of that period.
b) Indirect Funding
1) For the Participation Loan Program Application, the financial
intermediary staff will be responsible for the verification of the information
in the application. The Department staff will evaluate the information
submitted by the financial intermediary in order to determine that all
requirements of the application package have been addressed.
2) For the Loan Loss Reserve Program Application, the financial
intermediary staff will be responsible for the verification of the information
in the application.
3) For the Development Corporation Participation Program, the
financial intermediary staff will be responsible for the verification of the
information in the application. The Department staff will evaluate the
information submitted by the financial intermediary in order to determine that
all requirements of the application package have been addressed.
4) For the Rural Micro-businesses Participation Loan Program, in
addition to the requirements of subsection (b)(1) or (3), the Department:
A) will determine the amount, term, interest rate, and allowable
uses of each loan participation awarded; and
B) will allocate no less than 80% of the amount available for this
program for loans to businesses that are located in counties with a population
of 100,000 or less.