14 Ill. Adm. Code 680.230
Using Bid Credits
Section 680.230
Using Bid Credits
a)
Requesting Bid Credits for Use in a Bid
1)
Contractors and
subcontractors may request a Bid Credit Certificate from the Department to be
used for a bid on a specific project. The Bid Credit Certificate will identify
the amount of available bid credits that a contractor or subcontractor elects
to use for the project. Prior to July 1, 2027, the bid credit certificate will
only include credits earned in the project's region.
2)
The Bid Credit
Certificate may only be used in connection with the bid for the specific
project for which it is was requested.
3)
The bid credits
requested by the contractor or subcontractor for the Bid Credit Certificate
will be sequestered in the contractor or subcontractor's account and cannot be
used for more than one bid at a time bid.
b) Applying the Bid Credits
1) T
he awarding authority
for public works projects shall include language in the Invitation for Bid
specifically advising that contractors and their subcontractors may use Bid
Credits earned from the Illinois Works Jobs Program Act, including the maximum
amount of bid credits that can be used for the project as set forth in subsection
(d).
2)
Contractors shall
attach all Bid Credit Certificates to their bid for the public works project,
or as otherwise directed in the Invitation for Bid issued by the awarding authority.
3)
Bid credits are
used to lower the base bid of a contractor to outbid the lowest qualified and
responsible bidder who did not use bid credits by at least $1. The awarding authority
will only apply the amount of bid credits necessary for the contractor to
outbid the lowest qualified and responsible bidder by at least $1.
4)
The contractor
with the lowest effective bid will have the opportunity to accept the contract
at the bid amount that was submitted by the lowest qualified and responsible
bidder who did not use bid credits. For example, Contractor A submits a bid
for $1,000,000. Contractor B submits a bid for $1,050,000, but also uses
$60,000 Bid Credit Certificate. Contractor B's base bid is lowered to
$990,000, and would then have the opportunity to accept the contract at the
base bid submitted by Contractor A ($1,000,000).
5)
If the awarding authority
receives multiple bids from contractors who submit Bid Credit Certificates, the
contractor with the lowest effective bid will be selected as the prevailing
bidder, and will have the opportunity to accept the contract at the lowest base
bid amount.
6)
If the awarding authority
determines that two bidders have the same adjusted bid value, all pre-existing
selection criteria shall apply to select the prevailing bidder. No preference
shall be afforded to the bidding party which submitted the most bid credits.
7)
The use of bid
credits shall not be treated as a procurement preference pursuant to the
Illinois Procurement Code [30 ILCS 500/45-5], and unless otherwise provided in
the Invitation for Bid, all applicable procurement preferences shall apply.
c) Combining Bid Credit
Certificates
1) Multiple Bid Credit
Certificates may be combined in a bid for a specific project.
2)
A contractor who combines its Bid Credit Certificate with
that of a subcontractor must use at least $5,000 of its own bid credits.
3)
In the event the
contractor accepts the contract from the awarding authority at a value below that
contractor's base bid, the difference between the contractor's base bid and the
price it accepts the contract at should be distributed proportionally among all
contractors and subcontractors that are part of the bid. The proportion of the
difference that is applied to each contractor should not be more than the
proportion of their share of the base bid. For example, prime contractor
submits a base bid of $1,000,000. That bid is comprised of subcontractor A's
bid of $200,000, subcontractor B's bid of $200,000, and subcontractor C's bid
of $100,000. Prime contractor used a Bid Credit Certificate of $100,000, which
consisted of prime contractor's $40,000 bid credits, subcontractor A's $30,000
bid credits, and subcontractor B's $30,000 bid credits. If prime contractor
accepts the contract at $900,000, then the prime contractor should receive
$450,000, subcontractor A should receive $180,000, and subcontractor C should
receive $90,000 of the overall contract amount.
4)
The contractor that submits a Bid Credit Certificate of a
subcontractor on a bid must use that subcontractor on the project for which the
bid is submitted, unless the subcontractor elects not to participate in the
project or is disqualified by the Awarding Authority.
5) A
subcontractor who elects not to participate in a project after the bid is
submitted shall forfeit their bid credits. The prevailing bid shall not be
disrupted, and the contractor will not be required to elicit or submit
additional bid credits.
6) In
the event that a subcontractor is disqualified by the Awarding Authority after
the bid is selected and during due diligence review, the credits contributed by
that disqualified subcontractor will not be returned.
The
prevailing bid shall not be disrupted, and the prime contractor will not be
required to elicit or submit additional bid credits.
d)
Maximum Permitted Credit Usage. The maximum amount of bid
credits that may be used for a specific project when bidding on a public works
project shall be as follows:
1)
3% of the total project cost for projects that are $5
million or less.
2)
4%
of the total project cost for projects that are $50 million or less but more
than $5 million.
3) 5%
of the total project cost for projects more than $50 million.
e) Return
of Bid Credits
1) Bid
credits ultimately applied by an awarding authority will be subtracted from the
prevailing contractor or subcontractor's
account
at
the expiration of the protest period of the award. Any excess bid credits that
were not used by the awarding authority will be returned to the contractor or
subcontractor's account.
2)
In
the event that a bid contained multiple Bid Credit Certificates,
excess
bid credits shall be calculated, and ultimately returned to the parties that
submitted the Bid Credit Certificates, in a manner proportional to the original
contribution of each party. This provision shall not be construed to contravene
the requirement that a prime contractor must submit no less than $5,000 of its
own credits with each bid (see Section
680.230(c)(2)).
3)
Bid credits that were sequestered in an account will be
unfrozen if they are not accepted by the awarding authority, or if the
contractor or subcontractor withdraws its bid with the awarding authority and
returns the bid credit certificate to the Office of Illinois Works, or if the
Bid Credit Certificate expires. Contractors shall notify the Office of
Illinois Works if the bid credits are not accepted by the awarding authority
using a form provided by the Department. The Department will return the
sequestered bid credits to the contractors account within 10 business days of
receipt of notice.
4) Unless
the Department receives notice from the contractor or awarding authority that
the bid credits were not accepted or withdrawn, or unless additional time is requested
by the contractor to extend the duration of the Bid Credit Certificate, the
Bid Credit
Certificates shall expire 90 days after issuance. After expiration, the credits
will be returned to the contractor or subcontractor's account within 10 business
days.