77 Ill. Adm. Code 1110.120
Project Scope and Size, Utilization and Unfinished/Shell Space - Review Criteria
Section 1110.120 Project Scope and Size, Utilization and
Unfinished/Shell Space − Review Criteria
a) Size of Project – Review
Criteria
1) The
applicant shall document that the physical space proposed for the project is
necessary and appropriate. The proposed square footage cannot deviate from the
square footage range indicated in Appendix B, or exceed the square footage
standard in Appendix B if the standard is a single number, unless square
footage can be justified by documenting, as described in subsection (a)(2).
2) If
the project square footage is outside the standards in Appendix B, the
applicant shall submit architectural floor plans (see HFSRB NOTE) of the
project identifying all clinical service areas and those clinical service areas
or components of those areas that do not conform to the standards. The
applicant shall submit documentation of one or more of the following:
A) The
proposed space is appropriate and neither excessive nor deficient in relation
to the scope of services provided, as justified by clinical or operational
needs; supported by published data or studies, as available; and certified by
the facility's Medical Director; or
B) The
existing facility's physical configuration has constraints that require an
architectural design that exceeds the standards of Appendix B, as documented by
architectural drawings delineating the constraints or impediments, in
accordance with this subsection (a); or
C) Additional
space is mandated by governmental or certification agency requirements that
were not in existence when the Appendix B standards were adopted; or
D) The
project involves the conversion of existing space that results in excess square
footage.
HFSRB NOTE: Architectural floor
plans submitted shall identify clinical service areas or components and shall
designate the areas in square footage. Architectural floor plans must be of
sufficient accuracy and format to allow measurement. Format may be either a
digital drawing format (.dwg file or equivalent) or a measurable paper copy
1/16 scale or larger.
b) Project Services
Utilization − Review Criterion
The applicant shall document that,
by the end of the second year of operation, the annual utilization of the
clinical service areas or equipment shall meet or exceed the utilization
standards specified in Appendix B. The number of years projected shall not
exceed the number of historical years documented. If the applicant does not
meet the utilization standards in Appendix B, or if service areas do not have
utilization standards in 77 Ill. Adm. Code 1100, the applicant shall justify
its own utilization standard by providing published data or studies, as applicable
and available from a recognized source, that minimally include the following:
1) Clinical
encounter times for anticipated procedures in key rooms (for example, procedure
room, examination room, imaging room);
2) Preparation and
clean-up times, as appropriate;
3) Operational
availability (days/year and hours/day, for example 250 days/year and 8
hours/day); and
4) Other operational
factors.
c) Size of the Project and
Utilization:
For clinical service areas for
which norms are not listed in Appendix B (for example, central sterile supply,
laboratory, occupational therapy, pharmacy, physical therapy, respiratory
therapy, cardiac rehabilitation, speech pathology and audiology), the applicant
shall document that the proposed departmental gross square footage is necessary
and appropriate. The documentation shall consist of:
1) Basis
for the determination of the space (for example, key rooms, equipment,
personnel, utilization, etc.); and
2) Methodology applied.
d) Unfinished or Shell
Space − Review Criterion
If the project includes unfinished
space (i.e., shell space) that is to meet an anticipated future demand for
service, the applicant shall document that the amount of shell space proposed
for each department or clinical service area is justified, and that the space
will be consistent with the standards of Appendix B as stated in subsections
(a) and (b). The applicant shall provide the following information:
1) The
total gross square footage of the proposed shell space;
2) The
anticipated use of the shell space, specifying the proposed SF to be allocated
to each department, area or function;
3) Evidence
that the shell space is being constructed due to:
A) Requirements
of governmental or certification agencies; or
B) Experienced
increases in the historical occupancy or utilization of those departments,
areas or functions proposed to occupy the shell space. The applicant shall
provide the historical utilization for the department, area or function for the
latest 5-year period for which data are available, and, based upon the average
annual percentage increase for that period, project the future utilization of
the department, area or function through the anticipated date when the shell
space will be placed into operation.
e) Assurances
The applicant
shall submit the following:
1) The
applicant representative who signs the CON application shall submit a signed
and dated statement attesting to the applicant's understanding that, by the end
of the second year of operation after project completion, the applicant will
meet or exceed the utilization standards specified in Appendix B.
2) For
shell space, the applicant shall submit the following:
A) Verification
that the applicant will submit to HFSRB a CON application to develop and
utilize the shell space, regardless of the capital thresholds in effect at that
time or the categories of service involved;
B) The anticipated
date by which the subsequent CON application (to develop and utilize the
subject shell space) will be submitted; and
C) The estimated
date when the shell space will be completed and placed into operation.