77 Ill. Adm. Code 1130.570
Validity of an Exemption and Reporting Requirements
Section 1130
Section 1130.570 Validity of
an Exemption
and Reporting Requirements
a) A project that has received an exemption shall be completed on
or before the completion date approved by HFSRB or mandated by the Act and this
Part. An exemption shall be valid through completion provided the requirements
of this Section are met.
b) For
purposes of this Section, "completion" occurs on the following date:
1) for change of ownership of a health care facility, the date
that a new license has been issued (or, if licensing is not applicable, Medicare
and/or Medicaid certification has been obtained), or a stock transfer has been
accomplished, or a majority change in voting membership or sponsorship of a
not-for-profit corporation has been accomplished, or the transfer of assets has
occurred, or the merger or consolidation has been accomplished, whichever is
applicable;
2) for discontinuations, the date the entire health care facility
or category of service ceases operation, such as when the facility stops
providing services to patients or surrenders its license to the Department.
c) The exemption holder shall provide written notice and related
documentation to HFSRB of the following:
1) for
discontinuations, notice of project completion no later than 90 days following the
project completion date;
2) for
changes of ownership in which the applicant submitted key terms of the
transaction, certification that the transaction was or was not completed
according to the key terms contained in the application. The exemption holder must
submit the certification within 90 days after the closing date of the
transaction; and
3) for changes
of ownership in which the applicant submitted the final transaction documents, notice
of project completion, no later 90 days after the change of ownership.
d) An
exemption for a change of ownership of a health care facility shall be invalid
if the health care facility ceases to be an existing health care facility.
e) When
an applicant has submitted key terms of the transaction rather than final
transaction documents, an
exemption for a change of ownership
of a health
care facility shall be invalid if the exemption holder fails to
submit a
statement to the Board within 90 days after the closing date of the
transaction, or such longer period as provided by the Board, certifying that
the change of ownership has been completed in accordance with the key terms
contained in the application. If such key terms of the transaction change, a
new application is required
. [20 ILCS 3960/8.5(a)]
f) Other
events causing an exemption to become invalid include:
1) Change of permit (see
Section 1130.710(c));
2) Failure
to submit the Expenditure Commitment or Financial Commitment Report, which
should be included with the annual progress reports;
3) Failure to submit annual
progress reports to HFSRB;
4) Failure to submit Final
Cost Reports to HFSRB;
5) Implementation of a
prohibited alteration (see Section 1130.750(c)); and
6) Relinquishment of an
exemption without Board approval.
g)
The State Board may approve the transfer of an existing
permit without regard to whether the permit to be transferred has yet been
obligated, except for permits establishing a new facility or a new category of
service.
[20 ILCS 3960/6(b)]
h) Failure to comply with the requirements of this Section within
the specified time frames shall subject the exemption holder to the sanctions
and penalties provided by the Act (see 20 ILCS 3960/14.1) and Section 1130.790.
HFSRB NOTE:
See Section 1130.520 regarding changes of ownership for facilities with
outstanding permits.