77 Ill. Adm. Code 2030.210
Process
Section 2030
Section 2030.210 Process
When requesting a prior approval
required by this Part, the recipient shall address a written request to the
Department regional manager for the region or the "project officer"
as designated in the award document and to the Secretary of the Department. Approval
of the request shall be in writing and signed by either the Secretary or
his/her designee.
Recipients shall be responsible
for reviewing requests from their subrecipients to determine what approvals are
required by this Part and for giving or denying the approval. A recipient
shall not approve any action which is inconsistent with the purpose or terms of
the Department award. If an action by a subrecipient will result in a change
in the overall award or budget and therefore require Department approval, the
recipient shall obtain that approval before giving its approval to the
subrecipients. Approvals shall not be valid unless they are in writing and
signed by an authorized official of the recipient. Within 30 days from the
date of receipt of a request for approval, the Department shall review the
request and notify the recipient of its decision.