77 Ill. Adm. Code 225.8000
Applicability
Section 225
Section 225.8000Â
Applicability
a)Â Â Â Â Â Â Â Â When construction is contemplated, either for new buildings or
additions or major alterations (those that are not defined as minor alterations
in subsection (e) of this Section) to existing buildings coming within the
scope of these standards, design development drawings and outline
specifications shall be submitted to the Department for review. Approval will
be based on compliance with this Part. Approval of design development drawings
and specifications shall be obtained from the Department prior to starting
final working drawings and specifications. Comments or approval will be
provided within 30 days after receipt by the Department.
b)Â Â Â Â Â Â Â Â The final working drawings and specifications shall be
submitted to the Department for review and approval prior to beginning of
construction. For final approval to remain valid, contracts must be signed
within one year after the date of final approval. Alternate methods of design
development and construction such as fast track shall be acceptable if
equivalency can be proved. Comments or approval will be provided within 30
days after receipt by the Department.
c)Â Â Â Â Â Â Â Â Any contract modifications that affect or change the function,
design, or purpose of a facility shall be submitted to the Department for
approval prior to authorizing the modifications. Comments or approval will be
provided within 30 days after receipt by the Department.
d)Â Â Â Â Â Â Â Â The facility shall notify the Department at least 30 days
before construction has been completed. The Department will then complete a
final inspection. Deficiencies noted during the final inspection must be
corrected before occupancy will be allowed.
e)Â Â Â Â Â Â Â Â Minor alterations or remodeling changes that do not affect the
structural integrity of the building, that do not change functional operation,
that do not affect fire safety, and that do not add beds or facilities over
those for which the Model is licensed need not be submitted for drawing
approval.
f)Â Â Â Â Â Â Â Â No system of water supply, plumbing, sewage, garbage or refuse
disposal shall be installed, nor any such existing system materially altered or
extended until complete plans and specifications for the installation,
alteration or extension have been submitted to the Department and have been
reviewed and approved.