77 Ill. Adm. Code 340.1250
Reduction or Waiver of Penalties
Section 340
Section 340.1250Â Reduction
or Waiver of Penalties
a)Â Â Â Â Â Â Â Â When the Director finds that correction of a violation
required capital improvements or repairs in the physical plant of the facility
and the facility has a history of compliance with physical plant requirements,
the penalty will be reduced by the amount of the cost of the improvements or
repairs. This reduction, however, shall not reduce the penalty for a Type A
violation to an amount less than $1000.
b)Â Â Â Â Â Â Â Â Penalties resulting from Type B violations may be reduced or
waived only under one of the following conditions:
1)
The facility submits a true report of correction within ten
days
after the notice of violation is received, and the report is
subsequently verified by the Department. (Section 3-308(a) of the Act)
2)
The facility submits a plan of correction within ten days
after the notice of violation is received; the plan is approved by the
Department;
the facility submits a report of correction within 15 days
after submission of the plan of correction; and the report is subsequently
verified by the Department. (Section 3-308(b) of the Act)
3)
The facility submits a plan of correction within ten days
after the notice of a violation is received;
the plan provides for
correction time that is less than or equal to 30 days
after submission of
the plan of correction; and
the Department approves such plan
. (Section
3-308(c) of the Act)
4)Â Â Â Â Â Â Â Â Correction of the violation requires substantial capital
improvements or repairs in the physical plant of the facility;
the facility
submits a plan of correction for violations involving substantial capital
improvements which provides for correction within
90
days
after
submission of the plan, and the plan is approved by the Department. (Section
3-308(d) of the Act)