77 Ill. Adm. Code 570.1200
Reporting
Section 570.1200 Â Reporting
Failure of a grantee to comply with the requirements of this
Section shall result in the Department's withholding future grant funds to the
grantee (see Section 4.1 of the Illinois Grant Funds Recovery Act).
a)Â Â Â Â Â Â Â Â Quarterly
Progress Report. Each grantee shall submit (at a minimum) written progress
reports to the Department every three months. The reports are due within 10
calendar days after the quarterly reporting period has expired (see Section
4(b)(2) of the Illinois Grant Funds Recovery Act).
b)Â Â Â Â Â Â Â Â The
quarterly progress reports and annual reports shall include the following
information:
1)Â Â Â Â Â Â Â Â Current status of the
research project;
2)Â Â Â Â Â Â Â Â Project components
finished and project components yet to be finished;
3)Â Â Â Â Â Â Â Â Costs
incurred to date and an itemized listing of the total current estimated project
costs compared to the approved amounts;
4)Â Â Â Â Â Â Â Â Signature
of an authorized official of the grantee stating that this is a true and
complete report on the project's status; and
5)Â Â Â Â Â Â Â Â A
detailed report of how grant funds were expended.
c)Â Â Â Â Â Â Â Â Final
Report. Grantees shall submit a final report within 60 calendar days after the
conclusion of the grant period. The degree to which each objective in the grant
proposal has been met shall be fully addressed in this report. The final
report shall contain the following information:
1)Â Â Â Â Â Â Â Â A brief narrative
summarizing project accomplishments;
2)Â Â Â Â Â Â Â Â A
description of any problems that developed and how they were addressed;
3)Â Â Â Â Â Â Â Â A listing of all
project costs and sources of funds for the grant period.
4)Â Â Â Â Â Â Â Â A
certification, in the form of a notarized statement signed by an authorized
representative of the grantee, attesting that:
A)Â Â Â Â Â Â Â All
funds attributed to the grant have been expended;
B)Â Â Â Â Â Â Â The
costs reported are the final costs required to complete the research project
and there are no additional or associated costs; and
C)Â Â Â Â Â Â Â Funds
used for the project were approved by the Department.
5)Â Â Â Â Â Â Â Â A
grantee's failure to comply with the requirements of this Section will be
considered a material breach of the performance required by the grant agreement
and shall be the basis to initiate proceedings to recover all grant funds
disbursed to the grantee.