77 Ill. Adm. Code 845.300
Record Keeping Requirements for Lead Mitigation and Lead Abatement Activities
Section 845.300 Record Keeping Requirements for Lead
Mitigation and Lead Abatement Activities
a) The
lead abatement contractor shall retain the following information for every lead
abatement or lead mitigation project conducted in a regulated facility in Illinois:
1) The
name and address of the owner or its agent for whom the project was conducted;
2) A
copy of the 7-day notification form and all revisions submitted to the
Department prior to commencement;
3) Copies
of the results of any lead inspection or lead risk assessment conducted in the
regulated facility;
4) A signed
copy of the Work Practice and Occupant Protection Plan developed for the
regulated facility;
5) A
copy of the written personal protection plan for the project;
6) A
list of the names of the licensed lead abatement workers and lead abatement supervisors
employed for each project, including a copy of their Department-issued lead
abatement license;
7) A
copy of the written assurance statement provided by the licensed lead abatement
supervisor as required in Section 845.155; and
8) A
copy of the final clearance evaluation results required by Section 845.225.
b) The
records shall be retained for at least 6 years from the date the lead
mitigation or lead abatement project was completed.
c) The
lead abatement contractor shall provide a copy of the items listed in subsections
(a)(1) through (8) to the owner of the regulated facility within 60 days after
completion of the lead mitigation and/or abatement project.
d) The
lead abatement contractor shall maintain the following records for as long as
the company is licensed:
1) Completed license
application form;
2) Proof
of liability insurance for all of the time that the lead abatement contractor
is licensed;
3) Medical monitoring
records for all employees;
4) Copies of all
correspondence from the Department; and
5) Records
of all legal proceedings, lawsuits or claims that have been filed or levied
against the lead abatement contractor during the time that it is licensed by
the Department as a lead abatement contractor.
e) The
lead abatement contractor shall allow the Department or delegate agency access
to records pertaining to all lead mitigation and lead abatement projects
conducted in regulated facilities.