77 Ill. Adm. Code 800.300
Permits
Section 800
Section 800.300Â Permits
Prior to construction of a new
campground, major alteration of an existing licensed campground or major
extension of an existing licensed campground, a permit shall be obtained from
the Department.
a)Â Â Â Â Â Â Â Â In addition to the application requirements in Section 4 of
the Act, applications and two sets of plans must be submitted to the Department
for permits for the construction of new buildings and facilities or alteration
of existing buildings and facilities and shall contain the following
information:
1)Â Â Â Â Â Â Â Â Identification of the recreational area involved and the
person or organization preparing the drawings and specifications;
2)Â Â Â Â Â Â Â Â A statement describing the scope of the work proposed and the
anticipated time schedule;
3)Â Â Â Â Â Â Â Â A dimensioned plot plan of the recreational area showing
location of all structures and improvements;
4)Â Â Â Â Â Â Â Â Drawings and/or specifications for proposed buildings or
structures that include all structural components and material specifications;
5)Â Â Â Â Â Â Â Â Detailed drawings and specifications of proposed potable water
source and/or distribution system construction and a general arrangement
drawing showing distances between components of the potable water system and
sources of potential contamination that complies with Subpart C;
6)Â Â Â Â Â Â Â Â Detailed drawings and specifications of proposed sewage system
construction, and a general arrangement drawing showing distances between
components of the sewage system and potable water systems or bodies of surface
water, data showing estimated volume of sewage flow, and soil percolation rates
for absorption fields. Where a permit has been obtained or applied for from
the Environmental Protection Agency or a unit of local government for
construction of a sewage disposal system, a copy of the permit or permit
application shall be submitted. All systems must be in compliance with Subpart
D.
7)Â Â Â Â Â Â Â Â Detailed drawings and specifications for proposed swimming
pool construction sealed by an engineer or architect licensed to practice in
Illinois, in accordance with Subpart G;
8)Â Â Â Â Â Â Â Â Detailed drawings and specifications for proposed bathing
beach construction, showing water shed area, location of components of sewage
systems within the water shed, area and volume of the lake or pond, slope of
the bottom of the swimming area, extent of sand or gravel bottom in the
swimming area, height of diving boards, depth of water in swimming and diving
areas, location or buoyed lines marking wading and swimming areas, proposed
bather loading, and turnover rate of the pond or lake, all in accordance with
Subpart G;
9)Â Â Â Â Â Â Â Â Detailed drawings and specifications for proposed recreational
equipment construction involving partial or total body contact in water;
10)Â Â Â Â Â Â Â Â Detailed drawings and specifications for proposed food
service establishment construction showing interior construction of the
building, floors, walls and ceiling as well as details of food handling
equipment to be installed, in accordance with Subpart E;
11)Â Â Â Â Â Â Â Â Drawings of proposed electrical distribution system
construction showing general arrangement, size and type of wiring, method of
grounding, over current protection, type of equipment and load calculations, in
accordance with Subpart O;
12)Â Â Â Â Â Â Â Â Drawings of proposed sewer and water piping within buildings
showing size and location of piping, fittings, and fixtures as well as
materials of construction, in accordance with the Illinois Plumbing Code; and
13)Â Â Â Â Â Â Â Â Drawings showing details of proposed boat handling facility
construction when applicable in accordance with Subpart L.
b)Â Â Â Â Â Â Â Â For projects requiring a construction permit, an engineer
licensed in accordance with the Professional Engineering Practice Act of 1989
shall stamp the plans for all electrical systems, which serve recreational
vehicles, non-community water supply systems, and sewage disposal systems
designed for flows greater than 1500 gallons per day. The plans for all
multiple family dwellings including dormitories and all commercial structures
utilized by the patrons such as dining facilities and activity buildings shall
be sealed by an architect registered in accordance with the Illinois
Architecture Practice Act of 1989.
c)Â Â Â Â Â Â Â Â The maximum designated number of campsites shall be specified
in the permit application. This figure shall not exceed the capacity of the
water and sewage systems provided.
d)Â Â Â Â Â Â Â Â Prior to the issuance of a construction permit, the permit
applicant shall submit with the application a completed "Special Flood
Hazard Area Request Form" provided by the Department. If the site is
within a Special Flood Hazard Area, the applicant shall forward to the Illinois
Department of Transportation's Division of Water Resources the plans for the
project. No project to be located in a Special Flood Hazard Area shall be
issued a permit without a statement or a copy of a statement from the Division
of Water Resources that the construction complies with the requirements of
Executive Order 2006-5, effective March 7, 2006. Construction of such items as
water wells, septic tanks, underground utilities, light poles, pavilions,
playground equipment, sidewalks and driveways as specified in Statewide Permit
Number 6 issued by the Illinois Department of Transportation, Division of Water
Resources, May 13, 1983 are exempt from the above requirements.
e)Â Â Â Â Â Â Â Â Prior to construction of a new campground, major alteration or
major extension of an existing campground, permits and zoning approval, except
on State or federal lands, required by local health departments and zoning boards
as well as other governmental units having jurisdiction shall be obtained.
f)Â Â Â Â Â Â Â Â A permit is not required when existing facilities are utilized
to activate a new campground. Plans indicating the general location of all
structures and utilities shall be submitted to the Department, and the existing
facilities will be inspected by the Department's field personnel for compliance
with this Part. Any violations identified during the inspection of the
facilities shall be corrected, and the facilities shall be brought into
essential compliance with this Part prior to the issuance of a license.
g)Â Â Â Â Â Â Â Â A permit is not required to repair a facility in a licensed
campground or to correct a violation of this Part when such repair or
correction is made to an existing facility, and does not result in expansion of
any existing appurtenance or structure.
h)Â Â Â Â Â Â Â Â Campgrounds that were constructed prior to July 1, 1986, and
not licensed by the Department shall provide prior to the issuance of a license
the information specified in Section 4 of the Act.
i)Â Â Â Â Â Â Â Â Â Construction at a campground less than a major extension or
major alteration shall not require a permit. However, prior to initiating
construction, the applicant shall advise the regional office of the Department which
serves the campground in writing of the scope of the extension. Appendix A
contains the addresses of the regional offices.
j)Â Â Â Â Â Â Â Â Â The construction of community water supply systems and
surface discharge sewage disposal systems with flows greater than 1,500 gallons
per day requires a construction permit from the Illinois Environmental
Protection Agency.