77 Ill. Adm. Code 820.100
Permits
Section 820
Section 820.100Â Permits
a)        Construction Permit. A construction permit shall be obtained
prior to beginning any construction, major alteration or installation of a
swimming facility.
b)Â Â Â Â Â Â Â Â Procedure to Obtain a Construction Permit
1)Â Â Â Â Â Â Â Â The owner or his or her representative shall contract with a
project designer from the Department's list of prequalified architects or prequalified
professional engineers (see http://www.idph.state.il.us/envhealth/swimmingpools.htm)
who shall submit a completed application for a construction permit to the
Department. The application forms are available from the Department.
2)Â Â Â Â Â Â Â Â One set of detailed construction plans and specifications,
each bearing the seal and signature of a prequalified engineer or architect
licensed to practice in Illinois, shall be submitted for initial review.Â
However, three sets of the drawings shall be submitted prior to the issuance of
a construction permit. These plans and specifications shall comply with the
following requirements:
A)Â Â Â Â Â Â Â All plans and specifications shall be clear, consistent and
legible and include the name of the project location, the scale in feet, the
north point and date.
B)Â Â Â Â Â Â Â Detailed plans shall consist of plan view, elevations, sections
and supplementary views and specifications. Dimensions and relative elevations
of structures and equipment, location and size of piping, water levels, ground
elevations, and pump curve or curves shall be included. The plans and specifications
shall indicate compliance with all applicable requirements.
C)Â Â Â Â Â Â Â No change in location or construction of the project shall be
made from plans and specifications that have been approved without first
submitting details of the proposed changes to the Department and receiving
subsequent approval.
3)Â Â Â Â Â Â Â Â Construction Requirements in Flood Plains
A)       Scope. All construction, major alteration or installation
shall be built in accordance with the flood damage prevention standards of the
Department of Natural Resources (Regulation of Construction within Flood
Plains).
B)       Verification of Compliance. When construction, major
alteration or installation is proposed in a flood plain, the applicant shall
determine if the site is in a Special Flood Hazard Area. The Special Flood
Hazard Area Location Request Form, available from the Department, shall be
completed and submitted to the Department. If the site is located in a Special
Flood Hazard Area, plans for the project shall be forwarded to the Illinois
Department of Natural Resources. No project to be located in a Special Flood
Hazard Area shall be approved without written approval from the Illinois
Department of Natural Resources.
c)        Revised Plans and Specifications. If Department review of the
submitted documentation identifies the need for correction to the plans,
specifications or both, corrected copies shall be submitted with the
appropriate fee stated in Appendix B.Tables F, G and H. If the revised
documentation is satisfactory pursuant to this Section, the Department will
issue a construction permit.
d)        Notification after the Issuance of a Construction Permit. Â
The facility owner or permit applicant shall notify the appropriate Department
regional office or authorized agent, as specified with the issuance of the
permit, when construction, major alteration or installation of the project has
been initiated and again when construction, major alteration or installation
has been completed.
1)Â Â Â Â Â Â Â Â An owner of a new swimming facility, or a facility that has
undergone construction or major alteration or replacement of the swimming
facility structure, shall not operate the swimming facility, or allow the
swimming facility to be operated, until the Department has issued a license to
operate. To apply for a license, an original license application form shall be
completed and submitted to the Department with the appropriate fee stated in
Appendix B.Tables F, G and H. The license applicant shall contact the
appropriate regional office to make arrangements for an inspection of the
facility after making application and ensuring that the facility is in an
operating condition and in compliance with this Part. A current license to
operate a swimming facility that is to undergo major alterations may be
suspended by the Department for the period of alteration when continued
operation poses a risk of harm to patrons of the swimming facility.
2)Â Â Â Â Â Â Â Â The owner, manager or other responsible party shall keep a set
of plans and specifications bearing the approval stamp of the Department at the
swimming facility after the project has been completed.
e)        Alterations or Repairs of Existing Facilities. Repairs or
remodeling of existing swimming facilities must be in compliance with design
requirements in this Part. Alterations that meet the definition of major
alteration (see Section 820.10) shall require a construction permit.
f)        Preliminary Concept Approval. The Department may review
innovative design concepts and other design features that are not in strict
compliance with this Part in advance of submission of plans and specifications
to assure that the proposed concept or design will meet the intent of this
Part. Preliminary concept reviews may be conducted at the request of the
project designer when the Department determines that an explanation of the
innovative concept would aid in its review.