77 Ill. Adm. Code 855.170
Project Manager Responsibilities, Air Sampling Professional Responsibilities and Laboratory Services
Section 855
Section 855.170Â Project
Manager Responsibilities, Air Sampling Professional Responsibilities and
Laboratory Services
a)Â Â Â Â Â Â Â Â Project Manager
1)Â Â Â Â Â Â Â Â The project manager shall be licensed by the Department in
accordance with Section 855.100. For asbestos abatement projects in schools,
the project manager shall be the building owner's designated representative,
and shall be responsible for carrying out the following activities:
A)Â Â Â Â Â Â Â Assist in the evaluation of bids and the selection of a
contractor.
B)Â Â Â Â Â Â Â Ensure that all project activities are conducted in accordance
with the requirements of the Asbestos Abatement Act and this Part and contract
document.
C)Â Â Â Â Â Â Â Be on-site whenever project activities are taking place.
D)Â Â Â Â Â Â Â Reject defective barriers and decontamination enclosure
systems.
E)Â Â Â Â Â Â Â Meet with the contractor daily to review work progress, discuss
problems and adjust procedures as appropriate.
F)Â Â Â Â Â Â Â Â Report on abatement activities to the building owner and/or
school board.
G)Â Â Â Â Â Â Â Request, review and maintain contractor submission according to
Sections 855.350 and 855.450.
H)Â Â Â Â Â Â Â Enter the abatement project at least once every two hours to
observe ongoing removal of asbestos-containing material.
2)Â Â Â Â Â Â Â Â For every decontamination enclosure system, there shall be one
project manager.
3)Â Â Â Â Â Â Â Â The project manager shall have the authority to stop any job
activities not performed in accordance with contract specifications and any
provisions of this Part. The building owner and Department shall be notified
verbally by the project manager within 24 hours after a work stoppage. A
written report shall be submitted to the building owner with a description of
the activity, reason for stoppage and possible means for correcting the
problem.
4)Â Â Â Â Â Â Â Â The project manager shall keep a daily log of onsite
observations concerning the contractor's compliance with activities required
under this Part. This log shall be legible and made available upon request at
all times to the school board or building owner, the architect/engineer,
contractor, and appropriate local, State and federal agencies.
5)Â Â Â Â Â Â Â Â For each asbestos abatement project, the project manager shall
prepare a comprehensive final report. The report shall be submitted to the
school board or building owner, the contractor, and the Department within 60
working days following completion of final clearance air monitoring. The
report shall contain the following items submitted in the following order, with
each item labeled:
A)Â Â Â Â Â Â Â Project Manager's Report Form provided by the Department.
B)Â Â Â Â Â Â Â Items submitted by the contractor under Section 855.350(a).
C)Â Â Â Â Â Â Â For clearance air samples, the location of the sample, date of
sample, start and end times of sampling, sampling air flow rate, volume of air
sampled, name and address of laboratory performing the analysis, and name and
signature of the analyst.
i)Â Â Â Â Â Â Â Â Â When final air clearance monitoring samples are analyzed by a
laboratory using transmission electron microscopy (TEM), a copy of the National
Voluntary Laboratory Accreditation Program (NVLAP) certificate for airborne
asbestos fibers analysis for the laboratory.
ii)Â Â Â Â Â Â Â Â When final air clearance air monitoring samples are analyzed
by Phase Contrast Microscopy (PCM) in a laboratory, a copy of Proficiency
Analytical Testing (PAT) Program year-to-date performance report for the
laboratory. The year-to-date performance report should be for the testing
round completed closest to the completion of the project, but prior to the
completion of the project.
iii)Â Â Â Â Â Â Â When final air clearance air monitoring samples are analyzed
by an analyst outside of a laboratory, a copy of the report of performance
testing under the (Asbestos Analyst Report) AAR Program for the analyst for the
testing round completed prior to the completion of the project, but not after
the completion of the project.
D)Â Â Â Â Â Â Â Names, license numbers and current training certificates for
asbestos abatement workers who conducted the abatement.
E)Â Â Â Â Â Â Â Name, address, and license number of asbestos abatement
contractor.
F)Â Â Â Â Â Â Â Â Names, addresses, license numbers, and initial and current
training certificates for the project designer, project manager, and
contractor's supervisor(s), and signature of the project manager.
G)Â Â Â Â Â Â Â Name, signature, and license number of each air sampling professional.
H)Â Â Â Â Â Â Â Log of negative pressure measurements taken by the contractor
for contained areas. The readable tape from the monometer shall serve as the
log.
I)Â Â Â Â Â Â Â Â Variance requests submitted to the Department, and the
Department's responses to those requests.
J)Â Â Â Â Â Â Â Â Locations, times and results of background, personal, and area
air samples taken prior to and during the project.
K)Â Â Â Â Â Â Â A detailed description, diagram or blueprint indicating the
location of ACBM abated, locations of barriers, and locations of
decontamination enclosures.
L)Â Â Â Â Â Â Â A detailed description of the project, including description of
abatement methods employed, reasons for the project and for selection of the
abatement methods, description of types and amounts of ACBM abated, and start and
completion dates of the project.
M)Â Â Â Â Â Â Daily log of observations made by the project manager, including
description of project activities, documentation of smoke testing of barriers
by the contractor, documentation of post-abatement visual inspection of each
work area, and description of procedure used during clearance air sampling.
N)Â Â Â Â Â Â Â Items submitted by the contractor under Section 855.350(c) and
(d).
O)Â Â Â Â Â Â Â For cleaning performed in accordance with Section
350.400(f)(1)(A), (D) and (E), the names of persons performing the cleaning,
the date and locations of the cleaning, and the methods used.
6)Â Â Â Â Â Â Â Â For each asbestos abatement project, the project manager shall
submit a completed Project Manager's Report Form provided by the Department
within ten working days following completion of clearance air monitoring. A
copy shall be inserted as the first page in the project manager's report.
7)Â Â Â Â Â Â Â Â If more than one project manager serves on a project, other
than as specified below, the person who oversees the completion of the project
shall be responsible for the project report and for submission of the Project
Manager's Report Form to the Department. For projects with multiple work
areas, each overseen by a different project manager, each project manager shall
be responsible for the report and the Project Manager's Report Form for the
part of the project in the work area for which he or she was responsible.Â
However, one comprehensive report for the entire project is acceptable.
b)Â Â Â Â Â Â Â Â Air Sampling Professional (ASP)
1)Â Â Â Â Â Â Â Â The air sampling professional shall be licensed by the
Department in accordance with Section 855.100. The air sampling professional
shall conduct or supervise all air sampling for the school board. All projects
greater than 160 square feet or 260 linear feet shall be analyzed by
Transmission Electron Microscopy (TEM). All other samples may be analyzed by
Phase Contrast Microscopy (PCM).
2)Â Â Â Â Â Â Â Â Area sampling shall be conducted using collection media and
procedures in accordance with NIOSH method 7400. The following schedule shall
be utilized for air sampling during the project in addition to any OSHA
compliance monitoring required to be conducted by the contractor:
A)Â Â Â Â Â Â Â Background air samples shall be collected and analyzed prior to
the start of project activities in order to determine background airborne fiber
concentrations. Samples shall be taken both inside and outside of the work area
to establish existing levels.
B)Â Â Â Â Â Â Â The following schedule of samples shall be required on a daily
basis once abatement activities begin. The size of the abatement activity will
have impact on the number of samples necessary to monitor the contractor's
activities. The following are required minimums:
i)Â Â Â Â Â Â Â Â Â Two area samples inside the work area;
ii)Â Â Â Â Â Â Â Â One personal sample inside the work area;
iii)Â Â Â Â Â Â Â Two area samples outside the work area in uncontaminated
areas of the building, including one at the entrance to the worker
decontamination enclosure; and
iv)Â Â Â Â Â Â Â One area sample at each discharge from negative pressure
ventilation equipment to the outside of the building.
C)Â Â Â Â Â Â Â Air monitoring results shall be documented and retained
on-site.
c)Â Â Â Â Â Â Â Â Analyst Services
1)Â Â Â Â Â Â Â Â When final clearance air monitoring samples are anlyzed by a
laboratory using TEM, the laboratory shall be accredited by the NIOSH National
Voluntary Laboratory Accreditation Program (NVLAP) for airbone asbestos fiber
analysis.
2)Â Â Â Â Â Â Â Â When final clearance air monitoring samples are analyzed by
PCM in a laboratory, the laboratory shall be considered proficient in asbestos
analysis by the American Industrial Hygiene Association (AIHA) Proficiency
Analytical Testing (PAT) Program for PCM.
3)Â Â Â Â Â Â Â Â When final air clearance air monitoring samples are analyzed
by an analyst outside of a laboratory, the analyst analyzing the samples shall
be considered proficient (board approved) by the American Industrial Hygiene
Association's (AIHA) Asbestos Analyst Registry (AAR) Program.
4)Â Â Â Â Â Â Â Â The period of time permitted between the collection of daily
air samples and the availability of results shall be less than 24 hours for
samples collected during abatement activities. Timetables for results of
clearance air samples shall be established by the school board or building
owner.
d)Â Â Â Â Â Â Â Â Project Manager/Air Sampling Professional Duties Combined
The project manager and air sampling professional shall be
two separate individuals for each contained area. Duties may only be combined
for abatement project activities when the contained area is less than or equal
to 10,000 square feet or less than or equal to 1,500 linear feet of pipe
insulation in one contained area and decontamination enclosure system.