77 Ill. Adm. Code 855.25
Alternative Procedures and Variances
Section 855
Section 855.25Â Alternative
Procedures and Variances
a)Â Â Â Â Â Â Â Â A variance may be requested by submitting a written proposal
to the Department a minimum of 20 days before the commencement of work. The
written proposal shall include a detailed description of the procedure(s) to be
used in lieu of the requirements of this Part. The capability of the
alternative procedure(s) to provide an orderly, efficient, and safe abatement
which ensures protection equivalent to that provided by this Part or to
otherwise satisfy the intent of this Part shall be the basis for approval or
denial of the variance. The Department shall notify the applicant in writing of
its decision to either grant or deny the variance within 20 days after receipt
of the request. The project manager shall keep the approved variance available
at the work site at all times.
b)Â Â Â Â Â Â Â Â Variances on abatement project activities shall be issued on a
per project basis. Variance requests shall bear the signature of the licensed
project designer. Variances shall be valid for 180 days from the date of
issuance.
c)Â Â Â Â Â Â Â Â A completed Request for Variance Cover Sheet form provided by
the Department shall be submitted with each variance request.