77 Ill. Adm. Code 905.190
Installation Approval
Section 905
Section 905.190Â Installation
Approval
a)Â Â Â Â Â Â Â Â Plan approval shall be obtained from the Department or local
authority prior to beginning any construction of a new private sewage disposal
system. A new private sewage disposal system shall consist of, but not
necessarily be limited to, the following:
1)Â Â Â Â Â Â Â Â A system where a septic tank is replaced or where a major
component of the system is removed or added. Examples of major components
would be the replacement or addition of an aeration unit, re-circulating  sand
filter, sand filter, seepage pit, seepage bed or waste stabilization pond.
2)Â Â Â Â Â Â Â Â A system where the size of the absorption field is increased
by 25% or more or where 25% or more of the existing absorption field is removed
and replaced with new piping and backfill material.
b)Â Â Â Â Â Â Â Â Requests for approval shall be submitted on the forms provided
by the Department or local authority. At a minimum, the necessary information that
shall be submitted to the Department or local authority for approval shall
consist of:
1)Â Â Â Â Â Â Â Â Plans or drawings to scale indicating lot size with dimensions
showing the location of the system and type of system to be constructed; the
dimensions and the length of lateral pipe to be installed, showing type of
backfill material if applicable; distances to water lines, water wells, potable
water storage tanks and buildings; site elevations and ground surface
elevations sufficient to determine the elevation of system components and the
slope of the ground surface; location of sanitary sewer, if available, within 300
feet of the property; and typical cross-section of the system.
2)Â Â Â Â Â Â Â Â Number of bedrooms or design volume.
3)Â Â Â Â Â Â Â Â Soil investigation results or percolation test results and the
separation distance from the trench bottom to a limiting layer. The private
sewage disposal system installation contractor or homeowner shall submit
information with the plan approval application or local authority permit
application that a limiting layer does not exist within the distances provided
in Section 905.60(a)(7).
4)Â Â Â Â Â Â Â Â Owner's name and address.
5)Â Â Â Â Â Â Â Â Name and signature of applicant.
c)Â Â Â Â Â Â Â Â The
applicant's signature serves as written acknowledgement that the property
owners are aware of and accept the responsibility to service and maintain the
private sewage disposal system in accordance with the Private Sewage Disposal
Licensing Act and this Part. If the owner of the site is a developer or
contractor, he or she shall notify the purchaser and the Department or the
Department's agent of the transfer of ownership and responsibility for
maintenance.
d)Â Â Â Â Â Â Â Â Persons who construct, install, repair or modify a private
sewage disposal system shall notify the Department or local authority at least
48 hours prior to commencement of the work.
e)Â Â Â Â Â Â Â Â If any person constructs, installs, repairs or modifies a
private sewage disposal system without complying with the requirements of
subsections (a) through (d) of this Section and backfills any portion of the
system or covers any portion of the system with earth, cinders, gravel, shale
or any other material that will prevent the Department or local authority from
viewing the system to determine compliance with this Part, the property owner
or private sewage disposal installation contractor shall uncover the backfilled
or covered portions of the system.
f)        Contractor Responsibility. The private sewage disposal
installation contractor is responsible for percolation test results and the
sewage disposal system that is designed and constructed using those results.Â
Acceptance of percolation tests from other sources does not relieve the
installation contractor from responsibility. The private sewage disposal
system installation contractor is also responsible for the following:
1)Â Â Â Â Â Â Â Â Constructing, installing, repairing, modifying, or maintaining
the private sewage disposal system in accordance with this Part;
2)Â Â Â Â Â Â Â Â Providing the results of soil classification information or
percolation tests used to design a private sewage disposal system to the
property owner and retaining copies of this information for at least 5 years;
3)Â Â Â Â Â Â Â Â Providing service to aerobic treatment plants at least equal
to Section 905.100(g); and
4)Â Â Â Â Â Â Â Â Assuring compliance with all codes that may apply to the
system, including the National Electrical Code.
g)        Soil Classifier Responsibility. The soil classifier or
Illinois licensed professional engineer shall be responsible for the accuracy
of the information from soil investigations used to design private sewage
disposal systems.