83 Ill. Adm. Code 302.30
Application for Certificate of Authority
Section 302.30 Application for Certificate of Authority
a) Prior
to any Owner or Operator or its agent initiating contact with any landowner
(the record owner of the land as disclosed by the records of the tax collector
of the county where the land is located) to negotiate the acquisition of an
easement in property or any interest in property, it shall file with the
Illinois Commerce Commission an application containing, in addition to the
matters set forth in Section 20(b) of the Act, a brief description of the
proposed project, a map of the route or route width showing either
the
specific route for the carbon dioxide pipeline
(including size of site and
width of easement to be sought), or
the project route width that identifies
the areas in which the pipeline would be located, with such route ranging from
the minimum width required for the pipeline right-of-way up to 200 feet in
width
[220 ILCS 75/20(d)], and pipeline length and diameter, and the
location of any above ground facilities (compressor stations, valves, etc.).
b)
When
an applicant files its application for a certificate of authority with the
Commission, it shall provide notice to each local government where the proposed
pipeline will be located and include a map of the proposed pipeline route. The
applicant shall also publish notice in a newspaper of general circulation in
each county where the proposed pipeline is located.
[220 ILCS 75/20(c)]
c) The
applicant shall include with the application, when filed with the Commission, a
list containing the name and address of each owner of record of the land along
the proposed route, or within a proposed project route width, as disclosed by
the records of the tax collector of the county in which the land is located, as
of not more than 30 days prior to the filing of the application.
Notice of
the filing of an application for a certificate of authority shall be provided
by the Commission
within 30 days after filing to the landowners along the
proposed route, or to the potentially affected landowners within a proposed
project route width.
[220 ILCS 75/20(e)] Notice shall include the time and
place scheduled for the initial hearing on the application, and shall include
the information required by Appendix A. This subsection's requirements for
notice to owners of record shall not be deemed jurisdictional and the omission
of the name and address of an owner of record from the list or lack of notice
shall in no way invalidate a subsequent order of the Commission relating to the
application.