83 Ill. Adm. Code 1325.500
Testing Procedures
Section 1325.500 Testing Procedures
a) The
9-1-1 Authority shall prepare a written test plan to be submitted as an exhibit
to the final plan filled with the Administrator, pursuant to Section 1325.205.
The test plan will explain how the 9-1-1 Authority plans to perform its testing
in conjunction with the 9-1-1 system providers and carriers.
b) The
9-1-1 Authority shall ensure that proper field testing and data verification
has been performed on access lines in the 9-1-1 service area as prescribed in
this subsection (b). The testing shall include each NXX for every
telecommunications carrier and for every ESN within each service area prior to
the 9-1-1 system being able to announce its availability to the public.
1) New
9-1-1 system, or a new 9-1-1 system consolidating with an existing 9-1-1
system: 10% of the new portion only shall be tested;
2) Change
of 9-1-1 system provider, conversion to NG9-1-1, consolidation of an ETSB with
a rerouting of calls to a different PSAP, and consolidation with a reduction of
PSAPs with the same ETSB: a sample of each exchange, 2 test calls per type of
service; i.e., each land-line carrier (2 calls each), each wireless carrier (2
calls each), each Interconnected VoIP provider (2 calls each, if known); and
3) Other
changes to a 9-1-1 system, not outlined in subsection (b)(1) or (2): testing
as directed by the Department's Office of the Statewide 9-1-1 Administrator.
c) The
9-1-1 system provider may not cut the 9-1-1 system live until the 9-1-1
traditional legacy service database is at a 1% or less error ratio, pursuant to
ETSA Section 750/15.4(d). Errors found during testing shall be corrected prior
to cutting the system live.
d) The
9-1-1 Authority is responsible for ongoing testing once the 9-1-1 system is
on-line and shall, at a minimum, include the following:
1) The
9-1-1 Authority shall conduct testing, including, but not limited to, the 9-1-1
database, networking, system overflow, system backup, default routing, and call
transfer on a continuing basis to ensure system integrity. The testing shall
be coordinated in advance and in conjunction with the 9‑1‑1 system
provider and carriers.
2) The
9-1-1 Authority and 9-1-1 system providers shall participate in coordinated
testing with the carriers when any of the following occurs:
A) New
central office switching installations;
B) E9-1-1
selective router or functional equivalent installations, upgrades or rehomes
(i.e., resetting of the network system);
C) NPA
(Numbering Plan Area) additions;
D) Migration
from one 9-1-1 system provider to another; and
E) Any
other event that affects 9-1-1.
3) Upon
request, after notification of implementation, the 9-1-1 Authority shall
perform coordinated testing with the private residential or business switch
operators.