83 Ill. Adm. Code 451.360
Commission Order in Proceedings under Subpart D
Section 451
Section 451.360 Commission
Order in Proceedings under Subpart D
The Commission shall issue an
order granting or denying an application filed under this Subpart D within 45
days after the date on which a complete application has been filed with the
Commission and notice of the application's filing is published in the Official
State Newspaper as provided by the Notice by Publication Act [715 ILCS 5],
provided that the Commission can extend the time for considering an application
filed under this Subpart D by up to 90 days, and can schedule a hearing on such
an application. The Commission shall extend the time for considering an
application and schedule a hearing if:
a) The applicant has proposed limitations on the number of
customers or the amount of load to be served;
b) A party to the application proceeding has formally requested
that the Commission hold hearings in a pleading that contains a verified prima
facie showing that one or more of the allegations or certifications in the
application is false or misleading; or
c) Other facts or circumstances exist that will necessitate
additional time or evidence in order to determine whether a certificate should
be issued.