Integrated Distribution Company Implementation Plan
Section 452
Section 452.220 Integrated
Distribution Company Implementation Plan
a) To seek Commission approval to operate as an Integrated
Distribution Company, an electric utility shall file a written plan by which it
will implement, and affirm its commitment to comply with, the provisions of
Subpart B before May 31, 2002. The implementation plan shall be sufficiently
detailed so that the Commission can reasonably ascertain the systems, policies
and practices that the electric utility will use to satisfy each of the
requirements in Subpart B.
b) Within 45 days after an electric utility files an
implementation plan with the Commission pursuant to subsection (a), the
Commission shall approve, reject, or initiate a hearing to investigate the
implementation plan. If the Commission takes no action within 45 days, the
implementation plan shall be deemed approved. If the Commission initiates a
hearing to investigate the implementation plan, intervention in accordance with
83 Ill. Adm. Code 200 shall be permitted. After the hearing, the Commission
shall approve the implementation plan as filed or as modified by the
Commission, or reject the implementation plan. In any order entered pursuant to
this subsection, the Commission shall set forth its reasons for approving or
rejecting an implementation plan.
c) In any order rejecting an implementation plan, the Commission
shall specify the date by which an electric utility shall be in compliance with
Subpart A. Within 45 days after the entry of a final order approving an
implementation plan, or within 45 days after the implementation plan is permitted
to go into effect without a Commission order pursuant to subsection (b), an
electric utility shall be in full compliance with all requirements of Subpart
B.
d) If the utility rejects any modifications made to an
implementation plan by the Commission, it shall notify the Commission of its
rejection within 10 days after the entry of the final order and submit an
implementation plan pursuant to Section 452.170 within 45 days after the entry
of a final order or within 45 days after a denial of any applications for
rehearing, whichever is later.
e) An electric utility may at any time elect to no longer qualify
as an Integrated Distribution Company. An electric utility making such an
election shall immediately file an implementation plan pursuant to Section 452.170
for Commission approval. Upon the filing of such a plan, an electric utility
shall be subject to all requirements of Subpart A of this Part.
f) Each IDC shall file with the Commission revisions to an
approved implementation plan within 7 days after revision or at such time as
designated by the Commission. The Commission may initiate a proceeding to
disallow or modify any revision; in that proceeding, the burden shall be upon
the IDC to demonstrate that the revision is consistent with the provisions of
this Subpart B.