83 Ill. Adm. Code 466.APPENDIX G
G Interconnection Facilities Study Agreement
Section 466.APPENDIX G Interconnection Facilities Study
Agreement
Interconnection
Facilities Study Agreement
This agreement ("Agreement")
is made and entered into this
day of
by and between
("interconnection customer"), as an
individual person, or as a
organized and existing under the
laws of the State of
, and
("Electric Distribution
Company" (EDC)), a
existing under the laws of the
State of Illinois. Interconnection customer and EDC each
may be referred to as a "Party", or collectively as the "Parties".
Recitals:
Whereas
, interconnection customer is proposing to
develop a distributed generation facility or modifying an existing distributed
generation facility consistent with the interconnection request
application form completed by
interconnection customer on
(Date)
; and
Whereas
, interconnection customer desires to
interconnect the distributed generation facility with EDC's electric
distribution system; and
Whereas
, EDC has completed an interconnection system
impact study and provided the results of said study to interconnection customer
(unless proceeding directly from Level 1, 2 or 3 review); and
Whereas
, interconnection customer has requested EDC
to perform an interconnection facilities study to specify and estimate the cost
of the equipment, engineering, procurement and construction work needed to
interconnect the distributed generation facility;
Now, therefore
, in consideration of and subject to
the mutual covenants contained in this Agreement, the Parties agree as follows:
1. All
terms defined in Section 466.30 of the Illinois Distributed Generation
Interconnection Standard shall have the meanings indicated in that Section when
used in this Agreement.
2. Interconnection
customer elects and EDC shall cause an interconnection facilities study
consistent with Section 466.120 of the Illinois Distributed Generation
Interconnection Standard.
3. The
scope of the interconnection facilities study shall be determined by the information
provided in Attachment A to this Agreement.
4. An interconnection
facilities study report (1) shall provide a description, estimated cost of
distribution upgrades, and a schedule for required facilities to interconnect
the distributed generation facility to EDC's electric distribution system; and
(2) shall address all issues identified in the interconnection system impact
study (or identified in this study if the system impact study is combined
herein).
5. Interconnection
customer shall provide a study deposit of 100% of the estimated non-binding
study costs at least 20 business days prior to the date upon which the study
commences.
6. In
cases where no distribution upgrades are required, the interconnection
facilities study shall be completed and the results shall be transmitted to
interconnection customer within 15 business days after this Agreement is signed
by the Parties. In cases where distribution upgrades are required, the
interconnection facilities study shall be completed and the results shall be
transmitted to interconnection customer within 30 business days after this
Agreement is signed by the Parties.
7. Study
fees shall be based on actual costs and will be invoiced to interconnection
customer after the study is transmitted to interconnection customer. The
invoice shall include an itemized listing of employee time and costs expended
on the study.
8. Interconnection
customer shall pay any actual study costs that exceed the deposit within 30
calendar days on receipt of the invoice. EDC shall refund any excess deposit
amount within 30 calendar days after the invoice.
In witness whereof, the Parties have caused this Agreement
to be duly executed by their duly authorized officers or agents on the day and
year first above written.
[Insert name of interconnection customer]
Signed:
Name (Printed):
Title:
[Insert name of EDC]
Signed:
Name (Printed):
Title:
Attachment A to
Interconnection Facilities Study Agreement
Minimum Information That Interconnection Customer Must
Provide With the Interconnection Facilities Study Agreement.
Provide location plan and simplified one-line diagram of the
distributed generation facilities.
For staged projects, please indicate size and location of planned
additional future generation.
On the one-line diagram, indicate the generation capacity
attached at each metering location. (Maximum load on CT/PT).
On the one-line diagram, indicate the location of auxiliary
power. (Minimum load on CT/PT) Amps.
One set of metering is required for each generation
connection to the EDC's electric distribution system.
Number of generation connections:
Will an alternate source of auxiliary power be available
during CT/PT maintenance?
Yes
No
Will a transfer bus on the generation side of the metering
require that each meter set be designed for the total distributed generation
capacity?
Yes
No
(Please indicate on the one-line diagram).
What type of control system or PLC will be located at the
distributed generation facility?
What protocol does the control system or PLC
use?
Please provide a scale drawing of the site. Indicate the
point of common coupling, distribution line, and property lines.
Number of third party
easements required for EDC's interconnection facilities:
To be completed in coordination with EDC.
Is the distributed generation facility located in EDC's
service area?
Yes
No
If No, please provide name of local provider:
Please provide the following proposed schedule dates:
Begin construction date:
Generator step-up
transformers receive back feed power date:
Generation testing date:
Commercial operation date: