83 Ill. Adm. Code 467.70
Interconnection Review Procedures
Section 467.70 Interconnection Review Procedures
a) The
applicant shall submit an interconnection request using Appendix B, along with
the application fee specified in Appendix B.
b) Within
10 business days after receipt of an interconnection request, the EDC shall
notify the applicant whether the request is complete. When the interconnection
request is not complete, the EDC shall provide the applicant with a written
list detailing the information required to complete the interconnection
request. When additional information is required and reasonable, the applicant
and the EDC shall agree on a schedule to provide the required information or
the interconnection request is considered withdrawn. The parties may agree to
extend the time for receipt of the additional information. The interconnection
request is deemed complete when the applicant has provided the required
information or the parties have agreed that the applicant may provide
additional information later.
c) The
queue position of an interconnection request is used to determine the cost
responsibility for the system upgrades and interconnection facilities necessary
to accommodate the interconnection. The EDC shall notify the applicant as to
its queue position.
1) If
the applicant amends the interconnection request in a manner requiring that the
EDC re-study the feasibility or impact of the interconnection, the
interconnection request shall receive a new queue position based on the date
that it was amended.
2) If an
EDC determines that other interconnection requests may affect the same
facilities on its electric distribution system or transmission system as the DER
facility either proposed or being revised in an applicant's interconnection
request, the EDC may study these requests together without regard to their
queue position. If an EDC considers interconnection requests together because
they both affect the same facilities on the electric distribution system or on
transmission networks, the EDC shall notify the applicant of that fact at the
time studies are initiated. If the EDC considers two or more interconnection
requests together, estimated costs allocated to each applicant shall not exceed
the estimated cost associated with the interconnection request had the EDC reviewed
the interconnection requests in sequence.
d) After
the interconnection request has been assigned a queue position, the following
procedures shall be followed to determine how a study review shall be
conducted:
1) The
EDC shall offer the applicant the related study agreement forms included in
Appendices C, D and E. By mutual agreement of the parties, the scoping
meeting, interconnection feasibility study, interconnection system impact
study, or interconnection facilities study provided for in a study review and
discussed in this Section may be waived or combined.
2) A
scoping meeting shall be held no later than 10 business days, or on a mutually
agreed upon date and time, after the EDC has notified the applicant that the
applicant has provided all the necessary information. The meeting's purpose is
to review the interconnection request and existing studies relevant to the
interconnection request.
3)
When the parties agree that an
interconnection feasibility study shall be performed, the EDC shall provide to
the applicant, no later than 10 business days
after the parties' agreement
or, if held, the scoping meeting, an interconnection feasibility study
agreement (see Appendix D). The interconnection feasibility study agreement
shall include an outline for the scope of the study and the study's estimated
cost. If the applicant does not sign and return the study agreement within 25
business days, the application shall be deemed withdrawn and the queue position
shall be forfeited.
4) When
the parties agree that an interconnection system impact study shall be
performed, the EDC shall provide to the applicant, no later than 10 business
days after the parties' agreement, an interconnection system impact study
agreement (see Appendix E). The interconnection system impact study agreement
shall include an outline for the study's scope and the study's estimated cost.
If the applicant does not sign and return the study agreement within 25
business days, the application shall be deemed withdrawn and the queue position
shall be forfeited.
5) When
the parties agree that an interconnection facilities study shall be performed,
the EDC shall provide to the applicant, no later than 10 business days after
parties' agreement, an interconnection facilities study agreement (see Appendix
F). The interconnection facilities study agreement shall include an outline for
the study's scope and the study's estimated cost. If the applicant does not
sign and return the study agreement within 25 business days, the application
shall be deemed withdrawn and the queue position shall be forfeited.
6) Interconnection
studies that the EDC conducts shall consider all other DER facilities that, on
the date the interconnection study is commenced, are directly interconnected
with the EDC's electric distribution system, have a higher queue position than
the request being studied, or have a valid and active interconnection
agreement.
7) If
the applicant signs and returns an interconnection study agreement, but
subsequently notifies the EDC that it will not continue with its proposed large
DER facility project for any reason, the EDC need not complete the study or
provide the applicant with study results.
e) The following guidelines
shall govern all required interconnection studies:
1) Unless
waived by an applicant, an interconnection feasibility study shall include
analyses to identify potential adverse system impacts that would result from
the proposed interconnection at the applicant's proposed point of
interconnection.
A) The
interconnection feasibility study shall include pertinent elements from among
the following:
i) Initial
identification of any circuit breaker short circuit capability limits exceeded because
of the interconnection;
ii) Initial
identification of any thermal overload or voltage limit violations resulting
from the interconnection;
iii) Initial
review of grounding requirements and system protection; and
iv) Description
of, and non-binding estimated cost and construction schedule of, facilities
required to interconnect the DER facility to the EDC's electric distribution
system in a safe and reliable manner, including identification of potential
increased expenses due to location, distribution system assets, or other
relevant factors. Cost estimates provided in each instance must be itemized in
line item format and must break down costs by equipment, labor and other cost
categories. The cost estimates must also provide the component parts for
direct, indirect, and other identified cost categories.
B) If an
applicant requests that the interconnection feasibility study evaluates
multiple potential points of interconnection, additional evaluations may be
required. Additional evaluations shall be paid for by the applicant.
C) An
interconnection system impact study is not required when the interconnection
feasibility study concludes that there is no adverse system impact, or when the
study identifies an adverse system impact, but the EDC is able to identify a
remedy without the need for an interconnection system impact study.
D) A
study results meeting will be held within 10 business days after study
completion, if requested by the applicant. The study results meeting will be
attended by technical representatives of the EDC and the applicant. The study
results meeting shall not relieve the applicant from its obligations, nor does
it toll the clock for the applicant, to take the actions required by the rules
at that point of review.
E) The
parties shall use an interconnection feasibility study agreement, included as
Appendix D, unless both parties agree to use an alternative form.
2) An
interconnection system impact study evaluates the impact of the proposed interconnection
on both the safety and reliability of the EDC's electric distribution and
transmission system. This study identifies and sets forth in detail what system
impacts interconnecting a new or revising an existing DER facility to the
distribution system would have on the electric distribution and transmission
system, if there were no system upgrades.
A) A
distribution interconnection system impact study shall be performed when a
potential adverse system impact is identified in the interconnection feasibility
study. The interconnection system impact study shall include pertinent elements
from among the following:
i) A
load flow study;
ii) Identification
of affected systems;
iii) A
short-circuit analysis;
iv) An
analysis of equipment interrupting ratings;
v) A
protection coordination study;
vi) Voltage
drop and flicker studies;
vii) A
stability analysis;
viii) Grounding
reviews;
ix) Impact
on system operation; and
x) Alternatives
for mitigating adverse system impacts on affected systems.
B) The
final interconnection system impact study report shall provide the following:
i) The
underlying assumptions of the study;
ii) A
summary of the analyses;
iii) The
results of the analyses, including detailed information on any impacts identified,
the drivers and reasons for those impacts, including load, voltage, thermal and
other limitations, as well as the boundaries of the impacts, to the extent
possible;
iv) A
list of any potential impediments to providing the requested interconnection
service and information regarding technical thresholds that drive modifications;
v) Required
distribution upgrades;
vi) A
non-binding estimate of cost and time to construct any required distribution
upgrades. Those cost estimates shall provide the component parts for direct,
indirect, and other identified cost categories. Cost estimates must be
itemized and must break down costs by equipment, labor, overhead and other cost
categories; and
vii) If
the cost estimate exceeds 50% of the estimated cost set forth in the
feasibility study, a written itemization, by equipment, labor, overhead and
other cost categories, of the component parts that increased in cost and a
detailed explanation for the cost increase.
C) The
parties shall use an interconnection impact study agreement, included as
Appendix E, unless both parties agree to use an alternative form.
3) The
interconnection facilities study shall be conducted as follows:
A) The
interconnection facilities study shall estimate the cost of the equipment,
engineering, procurement and construction work, including overheads, needed to
implement the conclusions of the interconnection feasibility study and the
interconnection system impact study. The interconnection facilities study shall
identify:
i) The
electrical switching configuration of the equipment, including transformer,
switchgear, meters and other station equipment;
ii) The
nature and estimated cost of the EDC's interconnection facilities and system
upgrades necessary to accomplish the interconnection; and
iii) An
estimate for the time required to complete the construction and installation of
the facilities.
B) The
EDC may agree to permit an applicant to arrange for a third party to design and
construct the required interconnection facilities. In such a case, the EDC
shall make all relevant information and required specifications available to
the applicant to permit the applicant to obtain an independent design and cost
estimate for the facilities, which shall be built in accordance with the EDC's
specifications. The applicant shall ensure that any third party with whom it
shares the EDC's relevant information and required specifications shall comply
with applicable security and confidentiality requirements.
C) Upon
completion of the interconnection facilities study, and after the applicant
agrees to pay any just and reasonable costs for the interconnection facilities
and system upgrades identified in the interconnection facilities study, the EDC
shall provide to the applicant a standard DER interconnection agreement (see
Appendix C) for the applicant to sign. The applicant has 10 business days to
sign the agreement or the application is deemed withdrawn.
D) In the
event that system upgrades are identified in the impact study that shall be
added only in the event that higher-queued customers not yet interconnected
eventually complete and interconnect their generation facilities, the applicant
may elect to interconnect without paying for such upgrades at the time of the
interconnection, provided that it agrees to pay for the upgrades at the time
the higher-queued customer is ready to interconnect. If the applicant does not
pay for the upgrades at that time, the EDC shall require the applicant to
immediately disconnect its distribution generation facility to accommodate the
higher-queued customer.
E) The
parties shall use an interconnection facilities study agreement, included as
Appendix F, unless both parties agree to use an alternative form.
f) When
an EDC determines that it is appropriate to interconnect the DER facility, the
EDC shall provide the applicant with a standard DER interconnection agreement.
If the interconnection request is denied, the EDC shall provide the applicant
with a written explanation as to its reasons for denying interconnection. If
the EDC's written explanation demonstrates that the interconnection request was
denied for valid reasons, the interconnection request does not retain its queue
position.
g) Within
30 business days after receipt of the standard DER interconnection agreement,
the applicant shall provide all necessary information required of the applicant
by the agreement. The EDC shall develop all other information required of the
EDC by the agreement. After completing the agreement, the applicant shall sign
and return the agreement to the EDC. If the applicant does not sign and return
the agreement within 30 business days after its completion, the interconnection
request shall be deemed withdrawn, unless the applicant requests in writing to
have the deadline extended by no more than 15 business days. The initial
request for extension may not be denied by the EDC. If the applicant does not
sign the agreement after the 15-business-day extension, the interconnection
request shall be deemed withdrawn unless a further extension is agreed to by
the parties. The EDC shall return a fully executed DER interconnection
agreement within 10 business days. If withdrawn, the interconnection request
does not retain its queue position. When construction is required, the
interconnection of the DER facility shall proceed according to milestones
agreed to by the parties in the DER interconnection agreement.
h) The DER
facility is not permitted to operate until:
1) The
requirements of the interconnection agreement are satisfied; and
2) The DER
facility is approved by any electric code officials with jurisdiction over the
interconnection; and
3) The
applicant provides a certificate of completion (see Appendix A) to the EDC.
Completion of local inspections may be designated on inspection forms used by
local inspecting authorities; and
4) The
witness test is successfully completed if required by the EDC or if the witness
test is waived according to Article 2.1.1 of Appendix C.