83 Ill. Adm. Code 501.160
Testing Facilities and Equipment
Section 501.160 Testing Facilities and Equipment
a) A
utility shall provide laboratories, testing shops and other equipment,
facilities and personnel as may be necessary to conduct the tests required by
this Subpart or other orders of the Commission. A utility's laboratories, meter
testing shops, and other equipment and facilities so provided shall be at all
times available for inspection by authorized representatives of the Commission.
b) If a
utility selects an agent to perform meter sample testing, meter accuracy tests
when a meter is removed from service, and other requirements of this Subpart,
or if a utility changes its agent, or if the agent changes the location where
it will conduct meter tests, the utility shall notify the Director of the Safety
and Reliability Division of the Commission in writing within 60 days after the
selection or change. If an agent is selected or changed, the utility shall
provide the following information about the new agent:
1) Name of
agent;
2) Name of
contact for agent;
3) Address
and phone number of agent contact;
4) Address
of location where agent will conduct meter tests;
5) Summary
of meter types and sizes that agent will test;
6) Summary
of services the agent will perform for the utility; and
7) Identification
of what changes, if any, caused the need for the notification.
c) A
utility shall provide meter testing equipment, including a bell prover of not
less than two-cubic-foot capacity. A utility shall maintain each of its active
provers of all types in proper adjustment in order to determine the average
accuracy of meters to within one-half of one percent. A utility shall provide
suitable thermometers, pressure gauges, and temperature recorders and shall
adequately control the temperature of the meter testing room, meter soaking
room, and air supply used in testing meters to achieve the meter testing
accuracy stated in this subsection. The temperature of the meter testing and
soaking room, when in use, shall not vary by more than 4
°
F during regular operating hours and shall not vary by more
than 6
°
F throughout the year.
d) In
the event a meter shop experiences temperature variances that exceed those
provided in subsection (c), a utility shall immediately stop testing meters in
the meter shop until the utility corrects the problem and the temperature
returns to the normal levels for at least four continuous hours or the utility
can demonstrate that the temperature variance between the meters and testing
equipment is less than or equal to 1°F.
e) A
utility that uses a transfer prover to test the accuracy of meters in the field
shall verify the transfer prover's accuracy by testing a reference meter on the
transfer prover at least every three months. If this testing shows a deviation
of more than 0.5% in the reference meter accuracy, the utility must take all
necessary repairs or actions to bring the transfer prover's testing of the
reference meter to within 0.5% of the prior readings.
f) An
authorized representative of the Commission may check or establish the accuracy
of all testing equipment used or intended for use in determining the accuracy
of custody transfer meters, as well as the methods of operating that equipment.
If a utility uses an agent to test the accuracy of its meters, the utility
shall include provisions within its agreement with its agent for the authorized
representatives of the Commission to conduct on-site audits of the agent's
facility. An authorized representative of the Commission shall perform an audit
of the utility's testing equipment and methods at least every three years. The
utility shall reimburse the Commission for all expenses related to audits of
meter shops used or maintained by the utility or its agents located outside of
this State.
g) A
utility shall certify the accuracy of its testing equipment with measurement
results that are traceable to the international system of units through at
least one of the following national measurement institutes: the National
Institute of Standards and Technology for the United States, the National
Physical Laboratory for the United Kingdom, the National Research Council for
Canada, National Measurement Institute, American Association of Laboratory
Accreditation, and the Physikalisch-Technische Bundesanstalt for Germany.
Unless specified in this subsection (g), the maximum certification interval is
36 months.
1) A
utility shall certify sonic nozzle automatic provers at least every 12 months.
A utility shall also conduct the following maintenance at least every 12 months
on sonic nozzle automatic provers:
A) Inspect
and clean nozzles and solenoids;
B) Strap
and recertify a master bell during the bell interface recertification process;
C) Recalibrate
prover sensors and instrumentation in accordance with manufacturer's
specifications;
D) Test
the function of the optical sensor; and
E) Perform
a complete bell interface certification followed by a reference meter target
proof analysis.
2) Utility
verification checks on portable or reference equipment shall meet the following
requirements:
A) A
utility shall verify the accuracy of a portable standard against a reference
standard at least every 12 months. If the portable standard exhibits an error
greater than 0.5%, the utility shall adjust the portable standard to read
within 0.5% or replace the portable standard, or shall apply the proper
correction factor.
B) If a
utility does not operate a reference standard, the utility shall certify or
replace its portable standards at least every 12 months.
C) A
utility shall certify a reference standard at least every 36 months.
D) A
calibration certificate, verification certificate, or card signed or initialed
by the person responsible for the calibration shall accompany a portable
standard and a reference standard at all times. A utility, in lieu of
maintaining the certificate or card with the device, may maintain the
certificate or card in a central location or database that is available to
Commission Staff upon request. A certificate or card shall provide the date and
results of the last calibration or verification of the instrument. A utility,
after each successive issuance of certificates or cards, shall keep any
superseded certificates or cards on file for at least three years.
h) A
utility that tests meters with a rated capacity of 800 cubic feet per hour or
less shall use one or more reference meters to conduct equipment checks every
week. A utility shall designate and label reference meters for meter shop use
only, and shall not adjust reference meters in any manner once in service
unless they are in need of repair. A utility shall fully document all
alterations to a repaired reference meter, including before and after
accuracies. A reference meter shall carry a rating of 800 cubic feet per hour
or less and shall have a similar size to the meters the utility tests. Every
week during periods when a utility expects to test meters, a utility shall test
a reference meter on each prover that the utility uses to test meters of the
reference meter's size. A utility shall record reference meter test results,
including temperature, when testing on a sonic nozzle automatic prover, and
shall record the test results, temperature test flow times and bell pressure
when testing on a bell prover. If the reference meter tests indicate an
accuracy problem with any equipment, the utility shall cease using that
equipment until the utility repairs the equipment.
i) A
utility shall allow meters tested within a meter testing facility to acclimate
in the room containing the testing equipment or meter soaking room for at least
12 hours prior to testing. This acclimation time is not required if the utility
can show that it has taken sufficient actions to bring the meter temperature
and the testing equipment to within 1.0°F of each other.