83 Ill. Adm. Code 551.110
Commission Order in Proceedings
Section 551
Section 551.110 Commission Order in Proceedings
The Commission shall issue an order granting or denying an
application within 45 days after the date on which a complete application has
been filed with the Commission and notice of the application's filing is
published in the Official State Newspaper as provided by the Notice of
Publication Act [715 ILCS 5], provided that the Commission can extend the time
for considering an application filed under this Part by up to 90 days, and can
schedule a hearing on such an application. The Commission shall extend the time
for considering an application and schedule a hearing if:
a) The
applicant has proposed limitations on the number of residential or small
commercial customers or the amount of load to be served;
b) A
party to the application proceeding has formally requested that the Commission
hold hearings in a pleading that contains a verified prima facie showing that
one or more of the allegations or certifications in the application is false or
misleading;
c) Other
facts or circumstances exist that will necessitate additional time or evidence
in order to determine whether a certificate should be issued; or
d) The
applicant has proposed to serve an area smaller than the service area of a gas
utility.