83 Ill. Adm. Code 556.80
Approval or Withdrawal of QIP Surcharge Tariff
Section 556.80 Approval or Withdrawal of QIP Surcharge
Tariff
a)
The
Commission shall issue an order approving, or approving with modification to
ensure compliance with
Section 9-220.3 of the Act,
the
QIP surcharge
tariff no later than 120 days after such filing of the tariffs filed pursuant
to this
Part
. The utility shall have 7 days following the date of
service of the order to notify the Commission in writing whether it will accept
any modifications so identified in the order or whether it has elected not to
proceed with the tariff. If the order includes no modifications or if the
utility notifies the Commission that it will accept such modifications, the
QIP
surcharge
tariff shall take effect on the first day of the calendar year in
which the Commission issues the order, subject to petitions for rehearing and
appellate procedures.
[220 ILCS 5/9-220.3(a)(3)]
b) In
approving the QIP surcharge tariff for a utility having more than one rate
zone, the Commission may determine that it is appropriate for different QIP
surcharge tariffs to be applied in the different rate zones of the utility.
c)
After
the
QIP surcharge
tariff takes effect, the utility may, upon 10 days'
notice to the Commission, file to withdraw the
QIP surcharge
tariff at
any time, and the Commission shall approve such filing without suspension or
hearing, subject to a final reconciliation as provided in
Section 556.100.
[220 ILCS 5/9-220.3(a)(3)]
d)
When
a natural gas utility withdraws the
QIP surcharge
tariff, the utility
shall not recover any additional charges through the
QIP
surcharge
approved pursuant to this
Part,
subject to the resolution of the final
reconciliation. The utility's qualifying infrastructure investment net of
accumulated depreciation may be transferred to the natural gas utility's rate
base in the utility's next general rate case. The utility's delivery base
rates in effect upon withdrawal of the
QIP
surcharge tariff shall not be
adjusted at the time the
QIP
surcharge tariff is withdrawn.
[220
ILCS 5/9-220.3(a)(4)]