83 Ill. Adm. Code 731.635
Application of Level 1 Requirements to Level 2 Carriers and Conversion to Level 1
Section 731.635 Application of Level 1 Requirements to
Level 2 Carriers and Conversion to Level 1
If a Level 2 carrier is asked to or required to provide
wholesale services other than those set forth in Section 731.610, it must
petition the Commission for a determination as to whether it should be required
to comply with Level 1 requirements for the provision of the service or
services in question.
a) A
Level 2 carrier may be required to comply with some or all of the Level 1
requirements established in Subparts B, C, D, and E of this Part only after the
Commission considers and rules upon the following items:
1) The
technical feasibility of compliance with each Subpart B, C, D, and E
requirement;
2) The
economic feasibility of compliance with each Subpart B, C, D, and E
requirement;
3) The
expected volume of wholesale service activity to be provisioned by the Level 2
carrier;
4) Whether
the benefits expected to accrue to requesting carriers justify the costs
expected to be incurred by the provisioning carrier to comply with each Subpart
B, C, D, and E requirement; and
5) With
which Subpart B, C, D, and E requirements that carrier must comply and within
what time period.
b) A
carrier directed pursuant to a Commission order to comply with all of the
requirements of Subparts B, C, D, and E shall be a Level 1 carrier effective 90
days after the date of the Commission's order unless a different conversion
date is specified in the Commission's order. A carrier directed pursuant to a
Commission order to comply with some but not all of the requirements of
Subparts B, C, D, and E shall remain a Level 2 carrier, but shall, unless a
different time period is provided in the Commission's order, comply with such
Level 1 requirements as directed by the Commission commencing 90 days after the
date of the Commission's order.
c) In
any proceeding to determine whether a carrier should be required to comply with
some or all of the Level 1 requirements established in Subparts B, C, D, and E
of this Part, the Commission may order or establish an interim wholesale
service quality plan and determine its effective date.