83 Ill. Adm. Code 756.115
RFP Selection Process
Section 756
Section 756.115 RFP
Selection Process
a) The ITAC, on behalf of the carriers, shall develop and
circulate to prospective system providers an RFP for the provision of the relay
system through which telecommunications carriers shall provide the relay
service mandated by Section 13-703(b) of the Act and this Part.
1) The RFP shall require each respondent to submit a proposal for
the design, configuration and supply of a statewide relay system meeting or
exceeding the minimum specifications and standards prescribed in Sections
756.200, 756.205, 756.210 and 756.215.
2) The RFP shall require each respondent to supply, either
through direct provision or through the securing of services and facilities
provided by other entities, the following:
A) All relay center buildings, real estate, permits, rights-of-way
or clearances necessary to operate the relay system as specified in this Part;
B) All telecommunications trunks, cables or lines connected to the
relay center in order to receive or initiate telecommunications for the
purposes of providing the relay system as specified in this Part;
C) All telecommunications or other facilities and equipment
required in order to provide the relay system as specified in this Part;
D) All supplies, furniture or miscellaneous items required in
order to provide the relay system as specified in this Part; and
E) All personnel and the training of such personnel required in
order to staff and operate the relay system as specified in this Part.
3) The RFP shall state whether responses shall be based on a
cost-plus-fee or a fixed-cost type contract.
4) Prior to circulating the RFP to prospective system providers,
ITAC, on behalf of the carriers, shall file the RFP with the Commission for
approval, providing copies to the Advisory Council and Staff Liaison on the
file date.
A) The Advisory Council and Staff Liaison shall have the
opportunity to file comments on the RFP within 20 business days following the
file date of the RFP. The ITAC, on behalf of the carriers, shall be allowed
to respond to the comments within 10 business days following the close of the
comment period.
B) The Commission shall approve or disapprove the RFP for
circulation to prospective system providers by ITAC, on behalf of the carriers,
based upon the conformity of the RFP with the requirements of Section 13-703(b)
of the Act and this Part.
C) If the Commission disapproves the RFP, the Commission shall:
i) Specify those aspects which do not conform to the
specifications of this Part; and
ii) Direct ITAC, on behalf of the carriers, to revise the RFP in
regard to those elements.
5) System provider proposals shall be evaluated on the following
criteria:
A) The ability of a proposal to cost-effectively achieve the relay
system requirements prescribed by this Part;
B) A bidder's abilities to fulfill the conditions of its
proposal. The bidder shall be assessed according to its financial condition
(e.g., net worth, cash flow, and ability to raise capital); technical,
operational and managerial expertise; and past experience and level and quality
of performance.
C) A bidder's prior experience in providing relay services.
6) Each RFP will indicate a date, time, and place for prospective
system providers to submit a bid or proposal. Responses received late shall
not be considered.
7) All bids or proposals received prior to the time set for
opening shall be opened in public at the date, time, and place specified in the
RFP.
b) Evaluation procedure
1) Within two business days following the deadline for submission
of proposals by all parties, the ITAC, on behalf of the carriers, shall file
with the Commission and provide to the Advisory Council and Staff Liaison a
copy of each bid or proposal with a sworn statement by the president, a
vice-president or secretary of ITAC, on behalf of the carriers, stating that
said proposals are complete records and that they were received by ITAC under
seal which was not broken except as provided in subsection (a)(7);
2) If, after evaluating all proposals, the ITAC Board determines
that no proposals meet the requirements of Section 13-703(b) of the Act, this
Part, or the RFP, the ITAC, on behalf of the carriers, shall file with the
Commission notice of this determination and a report citing the specific
deficiencies of each proposal in adequately fulfilling the requirements of
Section 13-703(b) of the Act, this Part, or the RFP.
A) The Advisory Council and the Staff Liaison shall have the
opportunity to file comments on this report within 20 business days of filing
by ITAC, on behalf of the carriers. Comments in opposition to the ITAC, on
behalf of the carriers, determination shall cite and defend that proposal which
the commentator believes best meets or exceeds the requirements of Section
13-703(b) of the Act, this Part, and the RFP.
B) The ITAC Board shall have the opportunity to file a response to
the comments within 10 business days of the close of the comment period.
C) Based upon the requirements of Section 13-703(b) of the Act,
this Part, and the RFP, the Commission shall either:
i) approve the ITAC determination and direct ITAC to develop and
issue a new RFP according to the requirements of this Part, or to reissue its
prior RFP, or to request any or all bidders to supplement their proposals to
conform to the RFP; or
ii) deny the ITAC determination and specify a proposal which the
ITAC shall be directed to accept.